Alaköprü Dam

Coordinates: 36°10′53.05″N 32°53′44.55″E / 36.1814028°N 32.8957083°E / 36.1814028; 32.8957083
Source: Wikipedia, the free encyclopedia.
Alaköprü Dam
Annual generation
111.27 GWh

Alaköprü Dam (

Northern Cyprus Water Supply Project, to supply water for drinking and irrigation to Northern Cyprus.[2][3][4]

Preliminary construction on the dam began on November 2, 2010 and the official groundbreaking took place on March 7, 2011. After the completion of the 560 m (1,840 ft) long diversion tunnel, construction of the dam started on August 9, 2012 with placement of the foundation.[4][5] The dam was completed on schedule, on March 7, 2014 but its reservoir did not begin to collect water until February 2015.[6][7] The dam's 26 MW hydroelectric power station is expected to be commissioned in 2015.[8]

Up to 75,000,000 m3 (61,000 acre⋅ft) water from the dam's reservoir, which makes more than half of its capacity, will be transferred to Geçitköy Dam in Northern Cyprus via an 80 km (50 mi) pipeline crossing the Mediterranean Sea under 250 m (820 ft) depth.[4][5]

Part of the populated places in the area such as the villages of Sarıağaç, Akine, Çaltıbükü and Ormancık will be submerged in the reservoir of Alaköprü Dam.

See also

References

  1. ^ "Alaköprü Dam and HEPP" (in Turkish). Boyut Group. Archived from the original on 15 June 2013. Retrieved 10 May 2013.
  2. ^ "Alaköprü Barajı İnşaatı" (in Turkish). Ak-Eli İnşaat. Archived from the original on 2011-03-18. Retrieved 2012-10-13.
  3. ^ "Alaköprü Barajı". Haber Anamur (in Turkish). 2012-10-12. Retrieved 2012-10-13.
  4. ^ a b c "Alaköprü Barajı Su Derivasyonu Merasimi" (PDF) (in Turkish). DSİ. Archived from the original (PDF) on 2012-10-16. Retrieved 2012-10-13.
  5. ^ a b "Alaköprü Barajı'nda Derivasyon İşlemine Başlanıyor" (in Turkish). DSİ. 2012-08-09. Retrieved 2012-11-03.
  6. ^ "TRNC Water Supply Project giant step" (in Turkish). Anadolu Ajansi. Retrieved 22 December 2014.
  7. ^ "Alakopru Dam began to fill with water". Kibris. 16 February 2015. Retrieved 25 February 2015.
  8. ^ "Alaköprü DAM and HPP". Boyut Group. Archived from the original on 22 December 2014. Retrieved 22 December 2014.