General information | |
Status | Under construction |
Type | Office and retail |
Location | 600 108th Avenue Northeast Bellevue, Washington, U.S. |
Coordinates | 47°36′57″N 122°11′42″W / 47.61583°N 122.19500°W |
Construction started | March 2021 |
Estimated completion | 2024 |
Owner | Amazon |
Height | |
Architectural | 600 ft (180 m) |
Technical details | |
Floor count | 43 |
Floor area | 1,036,000 square feet (96,200 m2) |
Design and construction | |
Architecture firm | NBBJ |
Developer | Amazon |
Structural engineer | Magnusson Klemencic Associates |
Main contractor | Sellen Construction |
Other information | |
Parking | 1,175 spaces |
Bellevue 600 is a future
History
Bellevue 600 is planned to be located on a block bound to the south by Northeast 6th Street, to the west by 108th Avenue Northeast, and to the east by 110th Avenue Northeast. The Bellevue Corporate Center, a 10-story office building on the southwest corner of the block, was built in 1980 to serve as the regional office of
In February 2016, Seattle developer Touchstone and Chicago developer
Equity Commonwealth, a sister company to Equity Group, retained ownership of the Bellevue Corporate Center and the full 3.5-acre (1.4 ha) property and renovated the building in 2016. The property and project rights were sold to Amazon in April 2019 for $194.9 million through a shell corporation named Acorn Development.[9][10] A revised design plan from NBBJ for a 43-story office building was filed for permitting in July 2019, taking advantage of a city zoning change in 2017 that allows buildings with heights of up to 600 feet (180 m).[11] Amazon announced that it plans to begin construction in 2021 and open the building by 2024 as part of a major expansion into Bellevue with 15,000 total employees in the city.[12][13] The Bellevue city government granted planning approval for the first phase of the Bellevue 600 project in January 2021.[14] Construction began in March 2021 with demolition of the parking garage on the site.[15][16]
Design
The 43-story, 600-foot-tall (180 m) tower would be the tallest building in Bellevue and the tallest to be built by Amazon, surpassing its
A second tower on the southwest corner of the block, replacing the Bellevue Corporate Center, is also planned as part of the Bellevue 600 project.[12] It was initially proposed as a 33-story, 571-foot (174 m) office building, but was later reduced to 27 stories and 392 feet (119 m).[14] The second tower will have 764,000 square feet (71,000 m2) of office space, 13,800 square feet (1,280 m2) of retail and exhibition space on the ground floor, and a childcare center. Its underground parking garage—connected to the first building's garage—will have six levels with 718 stalls for cars and 1,000 stalls for bicycles.[19] Excavation for the second tower began in June, 2023, and is scheduled be completed by 2025.[20][21]
References
- ^ Bellevue 600 - Emporis https://www.emporis.com/buildings/1518504/bellevue-600-bellevue-wa-usa
- ^ a b c d Miller, Brian (April 10, 2017). "Touchstone gets MDP approval for 600 Bellevue project". Seattle Daily Journal of Commerce. Retrieved February 6, 2020.
- ^ Varney, Val (May 2, 1979). "Honeywell to make regional home here". The Seattle Times. p. H8.
- ^ "Around the Eastside: Police substation to open Monday". The Seattle Times. June 23, 2006. p. B3.
- ^ Stiles, Marc (March 10, 2015). "Chinese group lays out early plans for big downtown Bellevue property". Puget Sound Business Journal. Retrieved February 6, 2020.
- ^ Miller, Brian (March 22, 2018). "Plus sells majority stake in Elev8 to Stanford Hotels for $128M". Seattle Daily Journal of Commerce. Retrieved February 6, 2020.
- ^ "Touchstone eyes big project with two towers in Bellevue". Seattle Daily Journal of Commerce. February 26, 2016. Retrieved February 6, 2020.
- ^ Stiles, Marc (April 10, 2017). "Bellevue approves Sam Zell's plan for two new downtown towers". Puget Sound Business Journal. Retrieved February 6, 2020.
- ^ Rosenberg, Mike; Romano, Benjamin (April 24, 2019). "Amazon grabs large downtown Bellevue property next to transit hub". The Seattle Times. Retrieved February 6, 2020.
- ^ Stiles, Marc (January 4, 2019). "Source: Amazon 'most likely' buyer of prime downtown Bellevue property". Puget Sound Business Journal. Retrieved February 6, 2020.
- ^ a b Romano, Benjamin (July 2, 2019). "Amazon plans its tallest tower, marking growing presence in Bellevue". The Seattle Times. Retrieved February 6, 2020.
- ^ a b c d Stiles, Marc (January 29, 2020). "First look: Amazon's Bellevue 600 skyscrapers designed to be gateway". Puget Sound Business Journal. Retrieved February 6, 2020.
- ^ Romano, Benjamin (February 6, 2020). "Amazon plans for 15,000 employees in Bellevue". The Seattle Times. p. A1. Retrieved February 6, 2020.
- ^ a b Miller, Brian (January 11, 2021). "Amazon gets the OK for first Bellevue 600 office tower". Seattle Daily Journal of Commerce. Retrieved February 23, 2021.
- ^ Craigehad, Callie (March 31, 2021). "Construction on Amazon's Bellevue 600 office building begins as company expands presence on Eastside". Seattle Post-Intelligencer. Retrieved April 1, 2021.
- ^ Miller, Brian (March 30, 2021). "Work begins on Amazon's first Bellevue 600 tower". Seattle Daily Journal of Commerce. Retrieved April 1, 2021.
- ^ a b Miller, Brian (February 7, 2020). "More details emerge for 2-tower Amazon development in Bellevue". Seattle Daily Journal of Commerce. Retrieved February 8, 2020.
- ^ Stewart, Ashley (July 8, 2019). "Details about Amazon's Bellevue 600 project revealed in public records". Puget Sound Business Journal. Retrieved February 6, 2020.
- ^ Stiles, Marc (September 11, 2020). "Documents reveal early details of Amazon's Bellevue 600 second tower". Puget Sound Business Journal. Retrieved February 23, 2021.
- ^ "Project Update – Bellevue 600" (PDF). Sellen Construction. June 2023.
- ^ Miller, Brian (January 5, 2022). "Amazon's second Bellevue 600 tower gathers more steam". Seattle Daily Journal of Commerce. Retrieved April 1, 2022.
Further reading
- Sydney Franklin (July 9, 2019). "Amazon will build its tallest office tower ever in Bellevue, Washington". The Architect's Newspaper. New York, New York.