Prototype Fast Breeder Reactor

Coordinates: 12°33′11″N 80°10′24″E / 12.55306°N 80.17333°E / 12.55306; 80.17333
Source: Wikipedia, the free encyclopedia.

PFBR
Generation
AHWR-300 and Generation of electricity
Power (thermal)1253
Power (electric)500
Prototype Fast Breeder Reactor
Map
CountryIndia
LocationMadras
Coordinates12°33′11″N 80°10′24″E / 12.55306°N 80.17333°E / 12.55306; 80.17333
StatusUnder construction
Construction began2004
Commission dateOctober 2022 (planned)[3]
Construction cost5,850 crore (equivalent to 220 billion or US$2.69 billion in 2023)[3]
Owner(s)BHAVINI
Operator(s)BHAVINI
Nuclear power station
Reactor typefast breeder
Cooling source
Power generation
Nameplate capacity500 MW
]

The Prototype Fast Breeder Reactor (PFBR) is a 500 MWe fast breeder nuclear reactor presently being constructed at Kokkilamedu, near Kalpakkam, in Tamil Nadu state, India.[4] The Indira Gandhi Centre for Atomic Research (IGCAR) is responsible for the design of this reactor. The facility builds on the decades of experience gained from operating the lower power Fast Breeder Test Reactor (FBTR). At first, the reactor's construction was supposed to be completed in September 2010, but there were several delays. The Prototype Fast Breeder Reactor is scheduled to be put into service in December 2024, which is more than 20 years after construction began and 14 years after the original commissioning date, as of December 2023. The project's cost has doubled from ₹3,500 crore to ₹7,700 crore due to the multiple delays.

Background

The

three-stage nuclear power program
.

PFBR, with closed fuel cycle as the energy resource, is capable of generating a large amount of U-233 (a fissile isotope) from the abundant available thorium-232 within the country, to launch the third stage nuclear energy programme based on U-233 fuel cycle.[5]

India has the capability to use thorium cycle based processes to extract nuclear fuel. This is of special significance to the Indian nuclear power generation strategy as India has one of the world's largest reserves of thorium, which could provide power for more than 10,000 years,[6] and perhaps as long as 60,000 years.[7][8]

History

The design of this reactor was started in the 1980s, as a prototype for a 600 MW FBR. Construction of the first two FBR are planned at Kalpakkam, after a year of successful operation of the PFBR. Other four FBR are planned to follow beyond 2030, at sites to be defined.[9]

In 2007, the reactor was planned to begin its operation in 2010, but as of 2019, it was expected to reach first criticality in 2020.[10]

In July 2017, it was reported that the reactor is in final preparation to go critical.[11] However in August 2020, it was reported that the reactor might go critical only in December 2021.[12]

As of February 2021, around 6,840 crore (equivalent to 77 billion or US$961.21 million in 2023) have been spent in the construction and commissioning of the reactor. The reactor is now expected to be operational by October 2022.[3][13]

Prime Minister Narendra Modi was in Kalpakkam on 4 March 2024 to witness the initiation of its first core loading. A press release described the PFBR as marking the second stage of India's three-stage nuclear power program.[14]

Technical details

loss of coolant accident
situation.

The reactor is a

pool type LMFBR with 1,750 tonnes of sodium as coolant. Designed to generate 500 MWe of electrical power, with an operational life of 40 years, it will burn a mixed uranium-plutonium MOX fuel, a mixture of PuO
2
and UO
2
. A fuel burnup of 100 GWd/t is expected. The Fuel Fabrication Facility (FFF), under the direction of Bhabha Atomic Research Centre (BARC), Tarapur is responsible for the fuel rods manufacturing. FFF comes under "Nuclear Recycle Board" of Bhabha Atomic Research Center and has been responsible for fuel rod manufacturing of various types in the past.[citation needed] FFF Tarapur in early 2023 had successfully completed fabrication of 100,000 PFBR fuel elements[clarification needed].[15]

Safety considerations

The prototype fast breeder reactor has a negative void coefficient, thus ensuring a high level of passive nuclear safety. This means that when the reactor overheats (below the boiling point of sodium) the speed of the fission chain reaction decreases, lowering the power level and the temperature.[16] Similarly, before such a potential positive void condition may form from a complete

loss of coolant accident, sufficient coolant flow rates are made possible by the use of conventional pump inertia, alongside multiple inlet-perforations, to prevent the possible accident scenario of a single blockage halting coolant flow.[17]

The active-safety reactor

SCRAM
shutdown systems, designed to shut the fission reactions down effectively within a second, with the remaining decay heat then needing to be cooled for a number of hours by the 4 independent circuits.

The fact that the PFBR is cooled by liquid sodium creates additional safety requirements to isolate the coolant from the environment, especially in a

See also

  • FBR-600 Commercial variant of the PFBR design
  • India's three stage nuclear power programme

References

  1. ^ https://www.barc.gov.in/barc_nl/2022/2022030409.pdf
  2. ^ https://indianexpress.com/article/explained/india-first-indigenous-fast-breeder-reactor-kalpakkam-nuclear-9212492/
  3. ^ a b c "Lok Sabha Unstarred Question No. 330, Budget Session 2021" (PDF). Department of Atomic Energy, Government of India. 3 February 2021. Retrieved 18 April 2021.
  4. ^ Baldev Raj, S.C. Chetal and P. Chellapandi (8 January 2010). "Great expectations". Nuclear Engineering International.
  5. ^ https://www.onmanorama.com/news/india/2024/03/07/prototype-fast-breeder-reactor.html
  6. ^ Chris Rhodes (26 February 2012). "Thorium can power civilization for over 3000 years". Retrieved 23 March 2012.
  7. ^ MacKay, David J. C. (20 February 2009). Sustainable Energy - Without the Hot Air. UIT Cambridge Ltd. p. 166. Retrieved 23 March 2012.
  8. ^ Rodricks, Dan (9 May 2011). "Thor's nuclear-powered hammer". The Baltimore Sun. Retrieved 23 March 2012.
  9. ^ "India plans to construct six more fast breeder reactors". The Economic Times. 1 December 2015. Retrieved 15 December 2015.
  10. ^ "Prototype Fast Breeder Reactor at Kalpakkam in integrated commissioning stage". THEWEEK. 15 December 2021.
  11. ^ "Nuclear reactor at Kalpakkam: World's envy, India's pride". The Times of India. 26 November 2017. Retrieved 2 July 2017.
  12. ^ "India's First Prototype Fast Breeder Reactor Has a New Deadline. Should We Trust It?".
  13. ^ "Prototype Fast Breeder Reactor at Kalpakkam in integrated commissioning stage". The Week.
  14. ^ "Core loading of India's 1st indigenous nuclear reactor in Kalpakkam on Monday". The New Indian Express. 4 March 2024. Retrieved 4 March 2024.
  15. ^ Republic Day Address, BARC Director.
  16. S2CID 119918317
    .
  17. .
  18. ^ "Design of 500 MWe Prototype Fast Breeder Reactor" (PDF). Archived from the original (PDF) on 17 April 2012. Retrieved 17 April 2012.