Bermondsey dive-under
51°29′55″N 0°04′33″W / 51.4986°N 0.0757°W
The Bermondsey dive-under is a significant piece of rail infrastructure to the south of
History
Railway lines in south London wound over the docks and each other on
The first example of a flying junction in the United Kingdom was the Weaver Junction that opened on 13 November 1881. Here the grade separation was used to raise one track over the oncoming mainline on a double junction.[4]
In 2000, commuter services south of Thames were using the legacy tracks of a century earlier.
Construction history
Construction of the dive-under was complicated as existing services had to be maintained through the construction. Work commenced during 2013, with bridge-strengthening works near London Bridge station completed in June 2013.[5] The first track was used for services from 27 December 2016, two new lines for SouthEastern traffic came into service after the August bank holiday. The overall programme of work was scheduled to be completed in January 2018. [6] [7]
- 2011 the Borough Market viaduct was completed, doubling the available tracks to the west of London Bridge station, it was commissioned in January 2016.[8]
- Demolish Bricklayers Arms branch viaduct and rebuild to new profile in preparation for future use.
- Restricted timetable imposed
- Southeastern lines 3 & 4 were taken out of use and realigned. These were temporarily resignalled as lines 5 & 6, and used while lines 5 & 6 were taken out.
- Dive downs constructed. Side walls constructed. Piling.
- The dive-under box was built. This took a year to complete.
- Trackbed for the terminating Brighton slow downline laid and tested, and is operational on 27 December 2016 giving 3 line running capacity.
- Later, in August 2017, the Charing Cross tracks were diverted to their new permanent route using the dive-under, freeing the rest of the Southeastern part of the site for the installation of the final layout during 2018. At the same time work preparation was made for the new Thameslink dedicated tracks, ready to open the new through route via London Bridge.
- In January 2018 the new Thameslink London Bridge route opens. In December 2018, the timetable made its annual change. There are an additional 16 (tph) trains per hour through to Farringdon and St Pancras (previously 1 tph), 24tph in all including the new Luton to Rainham service.[9]
Description
Mainline railways around the South Bank | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
London Bridge is the fourth busiest station in the United Kingdom, serving around 54–56 million passengers a year.[10]
Previously, northbound Thameslink trains arrived into London Bridge to the south of the Kent lines. Thameslink trains needed to use the pair of tracks to the north, and Charing Cross trains needed to use the new pair of tracks to the south. The Brighton Main Line terminates here.
In simplest terms, the existing Charing Cross tracks dive under two tracks now reallocated to the new dedicated Thameslink service. Most tracks seen from above remain in roughly the same location as before though scheme there is a slight realignment to allow the two critical Thameslink and Charing Cross services routes to switch over from one side to the other. The changes to the vertical height of the tracks are significant. There are tight constraints both vertically and horizontally.[9]
The modification was undertaken to the east of London Bridge so that Thameslink trains from the Brighton Main Line can use a grade-separated crossover to avoid impeding trains from Kent bound for Charing Cross.[11][12] The Charing Cross services on the Kent lines are diverted slightly south in the vicinity of Trundleys Road onto the route of the former
References
- ^ Nock 1961, pp. 24 & 29.
- ^ Turner 1977, pp. 196–8.
- ^ Dendy Marshall 1963, p. 42.
- ISBN 0-900424-33-8.
- ^ "Thameslink: Strengthening works carried out for Bermondsey dive-under". Global Rail News.
- ^ "Passengers thanked as the first part of the Bermondsey Dive Under goes live". Archived from the original on 5 January 2017. Retrieved 25 July 2019.
- ^ "Award-winning Network Rail infrastructure project brings biodiversity to Bermondsey - Thameslink Programme". Archived from the original on 16 August 2017.
- ^ "Borough Viaduct | New Infrastructure". Thameslink Programme Learning Legacy. Retrieved 28 July 2019.
- ^ a b "Making the Grade (Separation): The Bermondsey Diveunder". London Reconnections. 2 August 2015. Retrieved 28 July 2019.
- ^ "New station control office unites rail staff at London Bridge as concourse opening approaches". Network Rail Media Centre. 2 June 2016. Retrieved 14 February 2018.
- ^ "Next step for London Bridge rail improvements as Bermondsey 'Diveunder' contract awarded - Thameslink Programme".
- ^ "Archived copy" (PDF). Archived from the original (PDF) on 4 March 2016. Retrieved 25 July 2019.
{{cite web}}
: CS1 maint: archived copy as title (link) - ^ "Bermondsey Dive Under | New Infrastructure". Thameslink Programme Learning Legacy. Retrieved 19 July 2019.
Bibliography
- Bonavia, Michael R. (1987). The history of the Southern Railway. London: Unwin Hyman. ISBN 0-04-385107-X.
- Brown, Joe (2015) [2006]. London Railway Atlas (4th ed.). ISBN 978-0-7110-3819-6.
- Dendy Marshall, C.F. (1963). A history of the Southern Railway vol.1 revised by R. W. Kidner. London: Ian Allan.
- Gray, Adrian (1977). The London and Brighton line 1841-1977. Oakwood Press.
- Nock, O.S. (1961). The South Eastern and Chatham Railway. London: Ian Allan.
- Turner, J.T. Howard (1977). London Brighton and South Coast Railway 1. Origins and formation. London: Batsford. ISBN 0-7134-0275-X.