CAREM

Coordinates: 33°58′04″S 59°12′47″W / 33.96769816066898°S 59.21303714281933°W / -33.96769816066898; -59.21303714281933
Source: Wikipedia, the free encyclopedia.
CAREM logo
Status of the construction of the CAREM plant in July 2019

CAREM (

Atucha I Nuclear Power Plant
.

Design

The reactor was integrally designed by CNEA (

core meltdown
, even in accident situations.

History

In 1984 it was presented publicly for the first time during an IAEA conference in Peru.[2] For political reasons the project was halted but was relaunched by the 2006 Argentine nuclear reactivation plan.

The 25

MWe prototype version of CAREM currently being built will be followed by a second one of 100–200 MWe to be installed in Formosa Province.[3][4]

As of 2013, the first prototype was planned to receive its first fuel load in 2017.[5] First concrete was poured in February 2014.[6]

As of 2016, the completion of the project was scheduled for the end of 2018.[7] Cost has been estimated to US$446[8]-700 million.[9] As of 2018, the start date was deferred to 2020.[10]

In November 2019, construction was halted due to late payments to the contractor, design changes and late delivery of technical documentation.[6] A new contract for finishing the concrete structures of the reactor was awarded in November 2021.[6]

See also

References

  1. ^ Office of Nuclear Energy, Science and Technology (May 2001). "Report to Congress on Small Modular Nuclear Reactors" (PDF). U.S. Department of Energy. Archived from the original (PDF) on 16 July 2011.
  2. ^ "El proyecto de reactor CAREM". Archived from the original on 2009-07-16. Retrieved 2010-06-10.
  3. ^ "Construction of CAREM underway". World Nuclear News. 10 February 2014. Retrieved 19 February 2014.
  4. ^ "El Plan Nuclear Argentino coloca a Formosa en destacado lugar frente a la construcción del CAREM". Archived from the original on 2011-07-20. Retrieved 2010-06-10.
  5. ^ "Contract awarded for CAREM vessel". World Nuclear News. 5 December 2013. Retrieved 6 December 2013.
  6. ^ a b c "Construction of Argentina's CAREM-25 unit to restart". World Nuclear News. 8 November 2021. Retrieved 9 May 2022.
  7. ^ "Contract for prototype CAREM balance of plant". World Nuclear News. 6 September 2016. Retrieved 6 December 2013.
  8. ^ "Nuclear Power in Argentina | Argentinian Nuclear Energy". www.world-nuclear.org. World Nuclear Association. April 2020. Archived from the original on 22 June 2020. The total cost was estimated at ARS 3.5 billion ($446 million).
  9. ^ Baker, Andrew. "Argentine nuclear reactor due to start up in..." BNamericas.com. Archived from the original on 30 March 2019.
  10. ^ "Progress for Argentina's CAREM vessel". Nuclear Engineering International. 9 May 2018. Retrieved 17 August 2019.

External links

33°58′04″S 59°12′47″W / 33.96769816066898°S 59.21303714281933°W / -33.96769816066898; -59.21303714281933

This page is based on the copyrighted Wikipedia article: CAREM. Articles is available under the CC BY-SA 3.0 license; additional terms may apply.Privacy Policy