Adelaide–Darwin railway line
The Adelaide–Darwin rail corridor consists of the 2975-kilometre (1849-mile) long
First steps towards a transcontinental railway
Under the provisions of the Northern Territory Acceptance Act 1910, the Commonwealth Railways assumed responsibility for the South Australian Railways' narrow gauge lines in the far north of South Australia and the Northern Territory. The Act mandated the building of a south–north railway although, crucially, no date was specified.[1][2] Two routes were considered: a standard gauge line branching off the Trans-Australian Railway at Tarcoola or a cheaper extension, from Oodnadatta, of the narrow gauge Central Australia Railway (CAR) line that had opened in 1891. Eventually the latter was chosen, and the extension to Alice Springs was opened in 1929.[3] Meanwhile, the North Australia Railway (NAR) opened in stages south from Darwin to Birdum, the latter being reached in 1929.[4]
In the late 1940s, the
: 133The northernmost two-thirds followed an alignment generally within 8 km (5 mi) of the narrow-gauge line. The southern third avoided the impediments of the mountainous section near Quorn and Hawker.[6][7] The new standard-gauge line covered one-third of the distance to Alice Springs, and a Commonwealth Railways booklet mentioned its "special importance to the Northern Territory as it is the first stage in the ultimate conversion of the narrow-gauge railway to Alice Springs to standard 4 ft 8+1⁄2 in gauge".[8]: 257
Tarcoola to Alice Springs
By 1967, interest in a transcontinental route had revived again. Extension of the route then in existence was one of three options considered, but a route far to the west, largely free of flood events, was chosen.[9] Construction of the current 828 km (515 mi) kilometre line from Tarcoola to Alice Springs began in April 1975, opening in October 1980. The CAR closed shortly after.[10][11] By then, the NAR had closed, in June 1976, following the closure of the iron ore mine at Frances Creek.[4]
Alice Springs to Darwin
In 1983, the
In June 1999, the
The Federal Government contributed $165 million from the Centenary of Federation Fund, the Northern Territory Government contributed $165 million and the South Australian Government contributed $150 million to the AustralAsia Rail Corporation for the construction of assets by the APTC and FreightLink that were later leased for a
In operation
FreightLink failed to make a profit in the first four years. In May 2008 the company announced that the board, shareholders and lenders had agreed to sell the company's ownership of the Alice Springs to Darwin line, citing its inheritance of a large amount of debt from the construction phase that it was unable to manage.[21][22][23] In November 2008, Freightlink went into voluntary administration after failing to reach agreement with creditors on the terms of a sale of the business.[24] Genesee & Wyoming Australia, later acquired by Aurizon, purchased the assets of FreightLink in June 2010 for $334 million, including the 50-year lease on the Tarcoola–Darwin line.[15][25]
As of 2022[update], the line from
Traffic
Two experiential tourism trains operate on the line: The Ghan service operated by Journey Beyond, which traverses the whole line and through to Adelaide weekly in each direction, with a scheduled duration of 53 hours 15 minutes;[30]: 108 and the company's Indian Pacific, an east–west service that runs on the southernmost 727 kilometres (452 miles) before heading west to Perth.
Aurizon is the only freight operator in the Tarcoola–Darwin section. Trains originate or terminate at intermodal terminals at Berrimah (Darwin) and Islington (Adelaide). They stop at intermodal points in Katherine, Tennant Creek and Alice Springs.[30]: 79
The line has facilitated bulk commodity exports from iron ore and copper mines in central Australia, including
Figures for Darwin's dry bulk exports illustrate the fickle nature of mining. In financial year 2010–11, export product delivered to Port Darwin by rail – comprising iron ore, manganese, and copper concentrate – exceeded 3 million tonnes for the first time.[34] With copper traffic ceased, the figure in 2013–14 for iron and manganese was 2.7 million tonnes. After mining of iron ore ceased in 2015–16, only manganese remained. In 2018–19, manganese exports totalled 900,000 tonnes.[35]
Since 2009 the company has hauled iron oxide / copper / gold ore mined at
During 2019, a large-scale track upgrade program was started between Adelaide and Tarcoola to allow heavier freight trains to operate at higher speeds. Rails were placed during the year[note 4] and finishing works such as replacing wooden sleepers with concrete ones were scheduled for 2020.[40]
Stations
The original CAR and NAR narrow-gauge lines had many small stations, sidings and halts along their routes for pick-up and set-down of wagons and less-than-car loads, and passengers, but freight traffic has been all-through on the post-2004 standard-gauge route. Stations only exist at Alice Springs, Tennant Creek, Katherine and Darwin.[41] Additionally there are crossing loops, most of them 1859 m (2000 yds) long: 12 south of Alice Springs and 3 to the north.[29]
See also
Notes
- ^ Train control is from Northgate block point, 6 km (3.7 mi) from Tarcoola, where the line diverges from the Trans-Australian Railway. It ends at Berrimah passenger terminal at Darwin. Northgate block point is 731 km (454 mi) from the Adelaide datum at Adelaide Parklands Terminal, near the Adelaide suburb of Keswick. Berrimah passenger terminal is 2,974 km (1,848 mi) from the Adelaide datum.
- ^ 29°43′38″S 135°34′01″E / 29.727286°S 135.567022°E.
- ^ 29°35′13″S 135°22′58″E / 29.586848°S 135.382827°E.
- ^ 70,000 tonnes of 60 kilograms per metre rails replaced 47 kg/m rail, increasing the axle load limit to 25 tonnes.
References
- ^ Northern Territory Acceptance Act 1910 Federal Register of Legislation
- ^ Northern Territory Acceptance Act 1910 Commonwealth of Australia Consolidated Acts
- ^ "Australian Commonwealth Railway Developments" Railway Gazette 28 January 1927 page 116
- ^ a b c d e History of the railway AustralAsia Railway Corporation
- ISBN 1877058483.
- ISBN 0-909650-49-7.
- ^ Port Augusta to Marree Chris's Commonwealth Railways
- ISBN 0727000160.
- Sydney Morning Herald. Retrieved 23 April 2017.").
subscription
: the source is only accessible via a paid subscription ("paywall - ^ "In Brief" Railway Gazette International June 1975 page 210
- ^ Standard Gauge to Alice Springs – Construction of Tarcoola–Alice Springs Railway Australian Railway Historical Society Bulletin June 1981 pages 117–139
- ^ "Preliminary work starts on 1500km Alice - Darwin link" Railway Gazette International April 1981 page 262
- ^ "Premier launches Alice - Darwin line" Railway Gazette International March 1983 page 152
- ^ Darwin deal Railway Gazette International July 1999
- ^ a b "Taxpayer funds sought from new rail owner". The World Today. Australian Broadcasting Corporation. 10 June 2010.
- ^ Industry unites at Australian showcase Railway Gazette International November 2003
- ^ "Transcontinental link is ready for business" Railway Gazette International January 2004 page 20
- ^ Australia's last frontier is conquered Railway Gazette International February 2004
- ^ "Completion of the Adelaide to Darwin railway line". Australian Bureau of Statistics. 8 December 2006.
- ^ First Train Archived 13 March 2018 at the Wayback Machine AustralAsia Railway Corporation
- ^ Calacouras, Nick (20 May 2008). "Railway up for sale". NT News. Darwin, Australia: Nationwide News Pty Limited.
- ^ Vesna Poljak and Michael Smith (19 May 2008). "Banks force sale of $1.2bn Adelaide-Darwin rail link". Australian Financial Review. p. 1 and 19.
- ^ Calacouras, Nick (20 May 2008). "Railway up for sale". Northern Territory News. News Ltd. Archived from the original on 21 July 2008. Retrieved 20 May 2008.
- ^ "End of the line as train sale derailed". Northern Territory News. News Ltd. 7 November 2008. Archived from the original on 12 February 2012. Retrieved 12 November 2008.
- ^ "FreightLink-owned Adelaide-Darwin railway to be sold to US company Genesee & Wyoming". The Advertiser. Adelaide. 9 June 2010. Retrieved 9 June 2010.
- ^ Our Network Australian Rail Track Corporation
- ^ Network map Archived 4 April 2015 at the Wayback Machine Genesee & Wyoming Australia
- ^ AustralAsia link making rapid progress Railway Gazette International 1 April 2002.
subscription
: the source is only accessible via a paid subscription ("paywall"). - ^ a b Vincent, Graham (2020). "Darwin line" (PDF). SA Track and Signal. Retrieved 19 December 2020.
- ^ a b "Trainline 6 Statistical Report" (PDF). Bureau of Infrastructure and Transport Research Economics. 2018. Retrieved 3 February 2021.
- ^ "First Prominent Hill shipment set for export". ABC News. 29 April 2009. Retrieved 30 May 2016.
- ^ "Train derailment copper concentrate recovered". ABC News. 17 January 2012. Retrieved 10 April 2016.
- ^ "Oz Minerals - Intermodal Solutions Group". Intermodal Solutions Group. Retrieved 30 May 2016.
- ^ "Dry Bulk Exports". Darwin Port. Archived from the original on 5 November 2016. Retrieved 30 May 2016.
- ^ "Dry bulk". Darwin Port. Darwin Port Operations Pty Ltd. 2019. Retrieved 24 August 2020.
- ^ First production from Prominent Hill copper-gold operation OZ Minerals ASX announcement, 26 February 2009. Accessed 12 January 2010.
- ^ "Monitor mining operations: South Australia". Mapbox. 2020. Retrieved 19 December 2020.
- ^ Vincent, Graham (2020). "Northgate-Wirrida" (PDF). SA Track and Signal. Retrieved 19 December 2020.
- ^ Vincent, Graham (2020). "Tarcoola" (PDF). SA Track and Signal. Retrieved 19 December 2020.
- ^ Powell, Jake (3 August 2020). "$252m rail upgrade contracts soon to be awarded". The flapping mouth. iSeekplant Pty Ltd. Retrieved 24 September 2020.
- ^ "Network Operating Guide, Part 32, Tarcoola to Darwin" (PDF). Australia Southern Railroad. 2 January 2004. Archived from the original (PDF) on 17 July 2011. Retrieved 10 June 2010.
Further reading
- Bromby, Robin (2004). Rails to the Top End: The Adelaide-Darwin Transcontinental Railway (4th ed.). Alice Springs: Paul Fitzsimons. ISBN 9780958176019.
- Rozycki, Jack (Jan–Mar 2003). "The Never Never Line. Australia's biggest project: the Adelaide-Darwin railway". Australian Geographic 69: 50–67.