Arnold Power Station

Coordinates: 42°31′44.58″S 171°24′40.56″E / 42.5290500°S 171.4112667°E / -42.5290500; 171.4112667
Source: Wikipedia, the free encyclopedia.

Arnold Power Station
TrustPower
Operator(s)
Power generation
Nameplate capacity3 MW (4,000 hp)
External links
CommonsRelated media on Commons
]
Weir dam at power station

The Arnold Power Station is a

TrustPower. Commissioned in 1932, the plant is rated at 3 megawatts (4,000 hp) and has an average annual output of 25 gigawatt-hours (90 TJ).[1]

History

Despite the pioneering achievements in supplying electricity to the town of Reefton in 1888, electricity was relatively late in coming to the settlements of the West Coast. The Grey Electric Power Board was established in October 1922, but at that stage, there was no immediate prospect of supply from the Government, and the Board was permitted to construct its own power scheme and associated transmission network. In 1923, a plan was developed to build a hydro-electric generating station on the Arnold River. However, to meet pressing demands for electricity supply from local residents this plan was postponed, and a coal-burning steam engine power station was built at Dobson in 1926.[2] However, after only a year's operation, the level of demand was such that more capacity was required, and the planning for the Arnold River hydro scheme recommenced. Construction began in October 1929, and the power station was opened in September 1932. Electricity from the station was transmitted at 33 kV.[2]

Technical details

The station was built with a concrete gravity dam, with an earth wing wall. An intake tunnel 11 feet (3.4 m) in diameter and 1,650 feet (500 m) long was built connecting to a surge chamber and two short penstocks. As originally constructed, the station had a head of 36 feet (11 m), but this was later increased to 42 feet (13 m). The Arnold station had two variable-pitch Kaplan turbines each driving generators rated at 1,500 kW.[3]

Connecting to the National Grid

The settlements of the West Coast did not finally receive a supply of electricity from the National Grid until October 1938, when a 66 kV transmission line was completed from Lake Coleridge across the Southern Alps through Arthur's Pass to the West Coast. In anticipation of becoming connected to the National Grid, in 1937 the Grey Electric Power Board agreed to sell the Arnold River hydro-electric power station to the Government, and also to surrender its right to generate power.[2]

Further development

TrustPower had been planning a new hydroelectric power station at Arnold, with an output of 46 megawatts (62,000 hp) and average annual generation of 220 gigawatt-hours (790 TJ).[4] Consents for this project were granted by the Grey District and West Coast Regional Councils in November 2008.[5] Though the resource consents were upheld by the Environment Court in 2010,[1] the project was put on hold indefinitely in 2012 due to changes in economic conditions.[6]

In September 2019 Trustpower said that the scheme was unlikely to proceed as it was not economically viable.[7] Consents for the scheme lapsed in December 2020.[8]

See also

References

  1. ^
    TrustPower. Archived from the original
    on 18 August 2013. Retrieved 25 May 2015.
  2. ^ .
  3. .
  4. ^ "Proposed Arnold Valley Hydro Electric Power Scheme". 17 November 2008. Archived from the original on 2 December 2008.
  5. ^ Kloeten, Niko (13 November 2008). "TrustPower gets consents for West Coast hydro scheme". National Business Review. Archived from the original on 11 June 2011. Retrieved 5 December 2008.
  6. ^ Kidson, Sally (23 May 2012). "Groups hail shelving of hydro schemes". The Nelson Mail. Archived from the original on 24 September 2015. Retrieved 25 May 2015.
  7. ^ Joanne Carroll (2 September 2019). "Consented hydroscheme for West Coast river not economically viable". Stuff. Archived from the original on 9 July 2021. Retrieved 1 July 2021.
  8. ^ "Arnold Power consents let go". Greymouth Star. 8 December 2020. Archived from the original on 10 July 2021. Retrieved 1 July 2021.