Line 5 (Chennai Metro)
Red Line (Line 5) | |
---|---|
Overview | |
Status | Under Construction |
Owner | standard gauge |
Electrification | 25 kV 50 Hz AC overhead catenary |
Operating speed | 80 km/h (50 mph) |
The Red Line or Line 5 is one of the three lines of Chennai Metro, Phase 2 Project. The under construction line stretches from Madhavaram Milk Colony to Sholinganallur. The line will consist of 45 stations, of which 6 are underground, 1 is at grade and 38 are elevated. The government has announced feasibility studies to extend metro rail's corridor-5 from Koyambedu to Pattabiram via Thirumangalam, Mogappair, Ambattur and Avadi. At present, the proposed corridor-5 links Madhavaram with Sholinganallur via Koyambedu, Alandur and Madipakkam.
Phase II
Of the three corridors in phase II, Line 5 features three crossovers, where the Metro trains run over the Porur and Medavakkam flyovers, the Kathipara grade separator and another yet-to-be built flyover between Mugalivakkam and Ramapuram.[3]
Line | Terminal | Length (km) |
Number of stations | Rolling stock | |
---|---|---|---|---|---|
Line 3 | Madhavaram Milk Colony | Siruseri Sipcot 2 | 45.4 kilometres (28.2 mi) | 48 | 56 trains of 3 cars each |
Line 4 | Poonamallee Depot | Lighthouse | 26.1 kilometres (16.2 mi) | 28[4] | 36 trains of 3 cars each |
Line 5 | Madhavaram Depot | Sholinganallur | 44.6 kilometres (27.7 mi) | 45 | 56 trains of 3 cars each |
Total | 116.1 km (72.1 mi) | 121 | 148 trains of 3 cars each. |
The present estimate for the phase 2 stands at Rs. 63,000 crore and received approval from the state government. Foundation stone for phase 2 was laid on 20 November 2020 by Union Home Minister Amit Shah and construction for the phase from Poonamallee to Power House of Line 4 commenced on 1 June 2021.[5][6] Addressing an event in Chennai, Prime Minister Narendra Modi on Sunday 14 February 2021 said the Centre has set aside Rs 63,000 crore in this year’s Budget for the second phase of Chennai Metro, which is one of the largest projects sanctioned for any city in one-go.[7] The map and list of stations for all 3 lines of Phase 2 has also been published by CMRL.
Feasibility reports for this line's branch extension for 16.07 km and Orange line's extension for 43.6 km is approved and DPR is under preparation, which will be ready by Jan 2025[8]. Phase 2 is expected to be completed by 2028.[9] Phase 2 will have trains with 138 three car trains making a total of 414 coaches.[10]
The stations in phase II will be smaller at 150 m (490 ft) compared with 220 m (720 ft) in phase I. Phase II will have three depots, namely, Madhavaram (27.8 hectares), SIPCOT (4.5 ha [11 acres]), and Poonamallee (15.4 ha [38 acres]).[11]
Stations
Red Line - Main | |||||
---|---|---|---|---|---|
S.No | Station Name | Connections | Layout | Opened | |
English | Tamil | ||||
1 | Madhavaram Milk Colony | மாதவரம் பால் பண்ணை | Purple Line |
Underground | UC |
2 | Madhavaram Depot | மாதவரம் பணிமனை | None | At-grade | UC |
3 | Assisi Nagar | அசிசி நகர் | None | Elevated | UC |
4 | Manjambakkam | மஞ்சம்பாக்கம் | None | Elevated | UC |
5 | Velmurugan Nagar | வேல்முருகன் நகர் | None | Elevated | UC |
6 | Madhavaram Bus Terminus | மாதவரம் பேருந்து நிலையம் | Madhavaram Mofussil Bus Terminus | Elevated | UC |
7 | Shastri Nagar, Chennai | சாஸ்திரி நகர் | None | Elevated | UC |
8 | Retteri Junction | ரெட்டேரி சந்திப்பு | None | Elevated | UC |
9 | Kolathur Junction | கொளத்தூர் சந்திப்பு | None | Underground | UC |
10 | Srinivasa Nagar | சீனிவாச நகர் | None | Underground | UC |
11 | Villivakkam | வில்லிவாக்கம் | Villivakkam railway station | Underground | UC |
12 | Villivakkam Bus Terminus | வில்லிவாக்கம் பேருந்து நிலையம் | Bus Terminus | Underground | UC |
13 | Villivakkam MTH Road | வில்லிவாக்கம் எம்.டி.எச் சாலை | None | Underground | UC |
14 | Anna Nagar West | அண்ணா நகர் மேற்கு | Bus Terminus | Elevated | UC |
15 | Thirumangalam | திருமங்கலம் | Green Line | Elevated | 15 May 2017 |
16 | Anna Nagar KV | அண்ணா நகர் கே.வி | None | Elevated | UC |
17 | Koyambedu | கோயம்பேடு | Green Line | Elevated | 29 June 2015 |
18 | Koyambedu Market | கோயம்பேடு அங்காடி | None | Elevated | UC |
19 | Natesan Nagar | நடேசன் நகர் | None | Elevated | UC |
20 | Virugambakkam | விருகம்பாக்கம் | None | Elevated | UC |
21 | Alwarthirunagar | ஆழ்வார்திருநகர் | Orange Line |
Elevated | UC |
22 | Valasaravakkam | வளசரவாக்கம் | Orange Line |
Elevated | UC |
23 | Karambakkam | காரம்பாக்கம் | Orange Line |
Elevated | UC |
24 | Alapakkam Junction | ஆலப்பாக்கம் சந்திப்பு | Orange Line |
Elevated | UC |
25 | Mugalivakkam | முகலிவாக்கம் | None | Elevated | UC |
26 | Ramapuram | ராமாபுரம் | None | Elevated | UC |
27 | Manapakkam | மணப்பாக்கம் | None | Elevated | UC |
28 | Chennai Trade Centre | சென்னை வர்த்தக மையம் | None | Elevated | UC |
29 | Butt Road | பட் சாலை | None | Elevated | UC |
30 | Arignar Anna Alandur |
அறிஞர் அண்ணா ஆலந்தூர் | Blue Line, Green Line | Elevated | 29 June 2015, 21 September 2016 |
31 | St. Thomas Mount |
பரங்கிமலை | Green Line, St. Thomas Mount railway station | Elevated | 14 October 2016 |
32 | Adambakkam | ஆதம்பாக்கம் | None | Elevated | UC |
33 | Vanuvampet | வானுவம்பேட்டை | None | Elevated | UC |
34 | Ullagaram | உள்ளகரம் | None | Elevated | UC |
35 | Madipakkam | மடிப்பாக்கம் | None | Elevated | UC |
36 | Kilkattalai | கீழ்க்கட்டளை | None | Elevated | UC |
37 | Echangadu | ஈச்சங்காடு | None | Elevated | UC |
38 | Kovilambakkam | கோவிலம்பாக்கம் | None | Elevated | UC |
39 | Vellakkal | வெள்ளக்கல் | None | Elevated | UC |
40 | Medavakkam I | மேடவாக்கம் I | None | Elevated | UC |
41 | Medavakkam II | மேடவாக்கம் II | None | Elevated | UC |
42 | Perumbakkam | பெரும்பாக்கம் | None | Elevated | UC |
43 | Classical Tamil Institute | செம்மொழித் தமிழாய்வு நிறுவனம் | None | Elevated | UC |
44 | Elcot | எல்காட் | None | Elevated | UC |
45 | Sholinganallur | சோழிங்கநல்லூர் | Purple Line |
Elevated | UC |
Red Line - Branch(Extension - Under Alignment Planning) | |||||
NA | Padi Pudhu Nagar | பாடி புதுநகர் | None | TBD | Proposed Phase 2 extension |
NA | Park Road | பாரக் சாலை | None | TBD | Proposed Phase 2 extension |
NA | Golden Colony | கோல்டன் காலனி | None | TBD | Proposed Phase 2 extension |
NA | Wavin | வாவின் | None | TBD | Proposed Phase 2 extension |
NA | Ambattur Estate | அம்பத்தூர் தொழிற்பேட்டை | Bus Terminus | TBD | Proposed Phase 2 extension |
NA | Ambattur Telephone Exchange | அம்பத்தூர் டெலிபோன் எக்ஸ்சேஞ்ச் | None | TBD | Proposed Phase 2 extension |
NA | Dunlop | டன்லப் | None | TBD | Proposed Phase 2 extension |
NA | Ambattur | அம்பத்தூர் | Ambattur railway station | TBD | Proposed Phase 2 extension |
NA | Ambattur OT | அம்பத்தூர் ஒடி | None | TBD | Proposed Phase 2 extension |
NA | Stedford Hospital | ஸ்டெட்போர்டு மருத்துவமனை | None | TBD | Proposed Phase 2 extension |
NA | Thirumullaivoyal | திருமுல்லைவாயல் | None | TBD | Proposed Phase 2 extension |
NA | Vaishnavi Nagar | வைஷ்ணவி நகர் | None | TBD | Proposed Phase 2 extension |
NA | Murugappa Polytechnic | முருகப்பா பால்டெக்னிக் | None | TBD | Proposed Phase 2 extension |
NA | Avadi | ஆவடி | Avadi railway station Bus Terminus |
TBD | Proposed Phase 2 extension |
NA | Hindu College | இந்து கல்லூரி | None | TBD | Proposed Phase 2 extension |
NA | Pattabiram | பட்டாபிராம் | None | TBD | Proposed Phase 2 extension |
Removed and renamed stations
Red Line | |||||||
---|---|---|---|---|---|---|---|
S.No | Old station name | Connections | Layout | New station name | |||
English | Tamil | English | Tamil | ||||
1 | Kaliamman Kovil Street | காளியம்மன் கோவில் தெரு | N/A | None | N/A | N/A | |
2 | Kamaraj Garden Street | காமராஜ் தோட்டம் சாலை | N/A | None | N/A | N/A | |
3 | Porur Junction | போரூர் சந்திப்பு | Orange Line |
Elevated | N/A | N/A | |
4 | CMBT | சி.எம்.பி.டி | Green Line Chennai Mofussil Bus Terminus | Elevated | Puratchi Thalaivi Dr. J. Jayalalithaa CMBT | புரட்சித் தலைவி டாக்டர் ஜெ. ஜெயலலிதா பேருந்து நிலையம் | |
5 | Venugopal Nagar | வேணுகோபால் நகர் | N/A | At-grade | Madhavaram Depot | மாதவரம் பணிமனை | |
6 | Nathamuni | நாதமுனி | N/A | Underground | Villivakkam MTH Road | வில்லிவாக்கம் எம்.டி.எச் சாலை | |
7 | Grain Market | தனிய அங்காடி | N/A | Elevated | Koyambedu Market | கோயம்பேடு அங்காடி | |
8 | Sai Nagar | சாய் நகர் | Bus Stop | Elevated | Natesan Nagar | நடேசன் நகர் | |
9 | Elango Nagar | இளங்கோ நகர் | Bus Stop | Elevated | Virugambakkam | விருகம்பாக்கம் | |
10 | DLF IT Park | டி.எல்.எஃப் தகவல் தொழில்நுட்ப பூங்கா | N/A | Elevated | Ramapuram | ராமாபுரம் | |
11 | Sathya Nagar | சத்தியா நகர் | N/A | Elevated | Manapakkam | மணப்பாக்கம் | |
12 | Puzhuthivakkam | புழுதிவாக்கம் | N/A | Elevated | Ullagaram | உள்ளகரம் | |
13 | Medavakkam Koot Road | மேடவாக்கம் கூட் ரோடு | N/A | Elevated | Medavakkam I | மேடவாக்கம் I | |
14 | Medavakkam Junction | மேடவாக்கம் சந்திப்பு | N/A | Elevated | Medavakkam II | மேடவாக்கம் II | |
15 | Global Hospital | குளோபல் மருத்துவமனை | N/A | Elevated | Classical Tamil Institute | செம்மொழித் தமிழாய்வு நிறுவனம் | |
16 | Alandur | ஆலந்தூர் | Blue Line, Green Line | Elevated | Arignar Anna Alandur | அறிஞர் அண்ணா ஆலந்தூர் |
References
- ^ Sekar, Sunitha. "104 km, 104 stations: Unveiling Phase II of Metro". The Hindu. Retrieved 24 January 2017.
- ^ "Metro's second phase to go up to Poonamallee". The Hindu. Chennai: Kasturi & Sons. 20 July 2017. Retrieved 1 October 2017.
- ^ Deepa H. Ramakrishnan and Sunitha Sekar (14 June 2021). "Chennai Metro phase II project will tower over 3 flyovers and Kathipara grade separator". The Hindu. Chennai: Kasturi & Sons. Retrieved 30 December 2021.
- ^ U, Tejonmayam. "Metro to link route planned under monorail network". The Times of India. Retrieved 17 February 2019.
- ^ Sekar, Sunitha. "Detailed project report for Phase II of Metro Rail ready". The Hindu. Retrieved 24 January 2017.
- ^ U, Tejonmayam. "Chennai: Metro rail to trim stations under phase 2". The Times of India. Retrieved 24 January 2017.
- ^ Dipak K, Dash. "Ground work for Chennai metro rail phase-2 hit". Times of India. Retrieved 19 February 2021.
- ^ "Koyambedu to Avadi: Bids Received for DPR of New Chennai Metro Corridor". Metro Rail News. Chennai. 24 April 2024.
{{cite news}}
: Unknown parameter|access date=
ignored (|access-date=
suggested) (help) - ^ "Metro Rail second phase likely to be completed in six years". The New Indian Express. Retrieved 26 April 2019.
- ^ Sekar, Sunitha (11 March 2019). "Chennai Metro phase II to have three-coach and six-coach trains". The Hindu. Chennai: Kasturi & Sons. p. 2. Retrieved 1 May 2019.
- ^ Sekar, Sunitha (25 April 2019). "For phase II, Chennai Metro will need less private land". The Hindu. Chennai: Kasturi & Sons. p. 3. Retrieved 2 May 2019.