SEPTA's 25 Hz traction power system

Source: Wikipedia, the free encyclopedia.
SEPTA Lansdale substation.

The

Southeastern Pennsylvania Transportation Authority (SEPTA) operates a 25 Hz traction power system in the vicinity of Philadelphia, that it inherited from the Reading Company. This system is separate from, but similar to, the system built by the Pennsylvania Railroad (PRR), which is now operated by Amtrak
. SEPTA's trains can run over either system because the voltage and frequency presented to the locomotive are essentially identical. However, the ex-Reading system is not electrically connected to the ex-PRR system.

SEPTA owns all of the substations described herein. Although SEPTA also owns former PRR substations along the Media/Wawa Line and the Chestnut Hill West Line, as well as a new substation just north of 30th Street Station, those facilities are electrically part of Amtrak's 25 Hz traction power system.

History

Electrification power infrastructure at Lansdale, Pennsylvania. 24 kV (top) feeders are directed into the substation and 12 kV feeders (bottom) return to the catenary.

The

Warminster in the early 1970s.[1][page needed
]

The Reading's system used catenary electrified at 12 kV 25 Hz like the competing

Wayne Junction. Although ownership and operation of the system has changed, the system has remained essentially unchanged with the exception of the replacement of the rotary converter station at Wayne Junction with a solid-state cycloconverter
in 1986.

Transmission system architecture

The Reading electrification system was designed for suburban MU operations and did not have to support the main line passenger or through freight operations of the rival Pennsylvania Railroad. While a complex system of high-voltage transmission lines was not necessary, the system was large enough to require the use of distribution feeders from the 25 Hz power supply at Wayne Junction. The feeders were set at 24 kV, double the traction voltage. Most of the rail lines would carry one or two feeders attached to the top of the catenary support masts. These 24 kV substation feeders can be distinguished from 12 kV traction feeders by the use of four-segment insulators as opposed to three-segment ones.

A simple schematic of the Reading autotransformer distribution scheme.[2]

The 24 kV lines feed a network of 11 substations (12 including the Wayne Junction switchyard) located every 8 to 10 miles (13 to 16 km) along the electrified rail lines. Most branches are short enough to only require a single substation near the end of the line, but the Main and West Trenton lines are long enough to require intermediate substations. At each substation the 24 kV feeders are fed through autotransformers to be reduced to the traction voltage of 12 kV, which is then passed through circuit breakers before being fed into the overhead catenary wires.

Power is transmitted, effectively, at 36 kV because the 24 kV and 12 kV components are 180° out of phase. This design has several advantages over the PRR's more traditional transmission and distribution scheme. The highest voltage, with respect to ground, within the system is 24 kV. This is significantly less than the 69 kV seen in the PRR's system, which required much larger 80 feet (24 m) towers and larger insulators and transformers. On a small system such as the Reading's, transmission infrastructure of this scale was unnecessary. Secondly, the system uses the 12 kV catenary wire for both transmission and distribution. This dual use of the catenary wire allows performing both functions with only two wires. The PRR's system in contrast required three wires: two for the single phase 138 kV transmission component and one for the 12 kV catenary feeder. In both systems, the rail is used as a return path for traction current.

Static frequency converters

Reading Railroad
.

All 25 Hz power on the ex-Reading system is generated at the

Jericho Park
converter.

The inverters replaced two ca. 1928 Westinghouse Electric motor generators that were each rated at 21.4 MVA. The capability also formerly existed to supply power from

motor-generators
normally used to supply the Pennsylvania Railroad's electrification system. This capability has been removed, as have the Somerset motor-generators. The ex-Reading system now operates completely independently from Amtrak's power system.

Wayne Junction receives 230 kV 60 Hz power from two redundant lines that connect to PECO substations at Waneeta, Tabor and Pulaski. Two 60 MVA 230/13.2 kV transformers reduce voltage for the static frequency converters. Cross-ties allow removing portions of the supply system from service for maintenance.

In March 2015 a contract worth $4,656,321 was awarded to

STV Incorporated, for the provision of architectural and engineering services for the rehabilitation of static frequency converters at Wayne Junction, with services to be performed over a period of 60 months scheduled to commence in April 2015 (per Proposal No. 14-233-JHC).[3]

Substations

25 Hz Power Supplies
on the ex-Reading System
Doylestown
Lansdale
Ambler
Hatboro
Yardley
Woodbourne
Neshaminy Falls
Bethayres
Jenkintown-Wyncote
Chestnut Hill East
Wayne Junction
Norristown
Fairmount
Girard Avenue
Legend
Converters and Switchyard
Substation
Future Substation
Phase break

Each of the former

American Brown Boveri
. Most transformers are rated to supply about 2 MVA of power each (a few 4 MVA transformers exist). Each substation also contained a number of oil-filled circuit breakers to disconnect both the 12 kV and 24 kV lines under load. The larger substations also have a small equipment and maintenance building to house any control equipment or secondary transformers for generating the 100 Hz signal power.

Replacement and renewal

Due to the robustness and simplicity of the components, until 2010 all the SEPTA substations were equipped with their original equipment, then approaching 80 years in service.

Callowhill / Fairmount

Callowhill substation was the first targeted for replacement, to eliminate the need to maintain the overhead wires over the abandoned Reading Viaduct rail line as feeders to the active tracks. Its replacement, Fairmount substation, was commissioned in the 3rd quarter of 2010,[4] featuring two 12/24 kV 25 Hz, single-phase 5 MVA autotransformers as well as trolley breakers and other switchgear.[5]

Norristown

Norristown substation received new transformers, trolley breakers, feeders, substation switchgear, protective relaying and a structural overhaul in a stimulus project.[6]

Wayne Junction

In July 2012, the US Department of Transportation awarded SEPTA a $12.8 million Tiger IV grant to help refurbish Wayne Junction Substation.[7] In the words of SEPTA General Manager Joseph M. Casey, "We intend to use these resources to replace equipment that should be on display in a museum of transit history."

The grant was announced at ceremony at the substation which was attended by Transportation Secretary Ray LaHood, who said "It's not the sexiest, it's not the prettiest, but it's one of the most important projects."[8]

Renewal of Wayne Junction's three static frequency converters is expected to occur during the 2010s, in three stages in order to maintain redundancy. A fourth converter is to be added for system security.[9][S 1]

In October 2014 SEPTA requested interested contractors to submit bids for the rehabilitation of the static frequency converters at Wayne Junction.[10]

Ambler

In September 2014 SEPTA requested interested contractors to submit bids for the rehabilitation of Ambler substation.[11] In October 2014 SEPTA awarded a $7.99 million contract to Carr & Duff, Inc.[12] for the work.[13]

Lansdale

On October 31, 2016, one of the substation's two main transformers burned out, and was replaced ahead of schedule a week later with one of the new transformers already on hand for the substation renewals at both Lansdale and Ambler.[14]

Doylestown

In the 1990s a fire at the Doylestown substation rendered it inoperable. Until the substation was repaired in 2013, the Doylestown Branch east of Lansdale had to be powered exclusively from the Lansdale substation. This "single-end feeding" of a 10-mile (16 km) section of track limited the number of MUs that could run simultaneously on the branch and also limited their maximum speed and acceleration.

The substation received a new 12/24 kV autotransformer in April 2015.[15]

Other substations

With the passage of a source of dedicated transportation funding by the Commonwealth of Pennsylvania, SEPTA announced in December 2013 a capital budget plan that includes renewal or replacement of all remaining former Reading substations, in five phases. The first phase involves replacement of Jenkintown substation and the renewal of Ambler substation's active components, projects for which final design had been completed by the end of 2013.[9][16]

In November 2014 SEPTA requested interested contractors to submit bids for the rehabilitation of four substations (Lansdale, Bethayres, Chestnut Hill East and Hatboro).[17] The engineering design work is expected to take two years, and the construction a further three years.

SEPTA also plans to build a new substation near

Woodbourne station by Fall 2020, as the distance between Neshaminy Falls and Yardley substations is nearly twice the optimal 5-mile (8.0 km) distance between substations on a 12 kV 25 Hz system.[S 2]

Substations on the ex-Reading System
Name Transformers Line Served Coordinates Notes
Ambler 1 Main Line 40°09′02″N 75°13′21″W / 40.15056°N 75.22250°W / 40.15056; -75.22250 (Ambler Substation) Designed for two transformers, but only one was ever installed.
Renewal designed and funded[16] Scheduled to be renewed by Summer 2016.[S 3]
Bethayres 1 West Trenton Line 40°06′57″N 75°04′07″W / 40.11583°N 75.06861°W / 40.11583; -75.06861 (Bethayres Substation) Scheduled to be renewed by Spring 2018.[S 4]
Callowhill
(Reading Terminal)
2 Main Line 39°57′31″N 75°09′26″W / 39.95861°N 75.15722°W / 39.95861; -75.15722 (Callowhill Substation) Replaced by Fairmount substation in 2010. Abandoned.
Chestnut Hill East 1 Chestnut Hill East Line 40°04′51″N 75°12′20″W / 40.08083°N 75.20556°W / 40.08083; -75.20556 (Chestnut Hill Substation) Originally had 2 transformers. Scheduled to be renewed by Summer 2018.[S 5]
Doylestown 1 Doylestown Branch 40°18′09″N 75°08′04″W / 40.30250°N 75.13444°W / 40.30250; -75.13444 (Doylestown Substation) Renewed Spring 2015.[S 6]
Fairmount 2 Main Line 39°57′55″N 75°09′07″W / 39.96528°N 75.15194°W / 39.96528; -75.15194 (Fairmount Substation) Built 2010, replaced Callowhill Substation.
Hatboro 1 Warminster Line 40°10′30″N 75°06′11″W / 40.17500°N 75.10306°W / 40.17500; -75.10306 (Hatboro Substation) Scheduled to be renewed by Winter 2020.[S 7]
Jenkintown 2 West Trenton and Main Lines 40°05′50″N 75°08′17″W / 40.09722°N 75.13806°W / 40.09722; -75.13806 (Jenkintown Substation) Replacement under construction; scheduled completion Fall 2016.[S 8]
Lansdale 2 Main Line 40°14′38″N 75°17′07″W / 40.24389°N 75.28528°W / 40.24389; -75.28528 (Lansdale Substation) Scheduled to be renewed by Summer 2017.[S 9]
Neshaminy Falls 2 West Trenton Line 40°08′45″N 74°57′54″W / 40.14583°N 74.96500°W / 40.14583; -74.96500 (Neshaminy Falls Substation) Scheduled to be renewed by Summer 2019.[S 10]
Norristown 2 Manayunk/Norristown Line 40°06′48″N 75°20′48″W / 40.11333°N 75.34667°W / 40.11333; -75.34667 (Norristown Substation) Feeders re-oriented 180° in 1970 for line relocation due to Dannehower Bridge (US 202) construction.
All substation components replaced 2012.
Wayne Junction 3 (step-up) All 40°01′31″N 75°09′23″W / 40.02528°N 75.15639°W / 40.02528; -75.15639 (Wayne Junction Switchyard) Design work is being undertaken to renew the electrical equipment at this site [7]
Woodbourne 2 West Trenton Line 40°11′34″N 74°53′21″W / 40.19278°N 74.88917°W / 40.19278; -74.88917 (Woodbourne Substation) New substation scheduled to be built by Fall 2020.[S 2]
Yardley 2 West Trenton Line 40°14′03″N 74°49′55″W / 40.23417°N 74.83194°W / 40.23417; -74.83194 (Yardley Substation) Scheduled to be renewed by Summer 2019.[S 11]

See also

Footnotes

General

  1. ^ Kneschke et al. (1995).
  2. ^ Kneschke et al. (1995), p. 80.
  3. ^ SEPTA (March 26, 2015). "Minutes of Regular Board Meeting (March 2015)" (PDF). SEPTA Board - Meeting Minutes. Retrieved 5 August 2015.
  4. ^ "Regional Rail Substation Improvements" (PDF). SEPTA Fiscal Year 2010 Capital Budget & Fiscal Years 2010-2021 Capital Program. SEPTA. Archived from the original (PDF) on 11 February 2013. Retrieved 5 September 2012.
  5. ^ "Fairmount Substation and 30th Street Switching Station". Gannett Fleming Transit & Rail Systems. Retrieved 5 September 2012.
  6. ^ "Norristown Power Substation Overhaul P2-2A". SEPTA Stimulus Project Information. SEPTA. Retrieved 5 September 2012.
  7. ^ a b "Wayne Junction Substation Update". www.SEPTA.org. Southeastern Pennsylvania Transportation Authority.
  8. ^ Quinn, Amy Z. (July 11, 2012). "Unsexy, but critically needed, replacement coming for Wayne Junction Substation". www.newsworks.org. Retrieved 5 August 2015.
  9. ^ a b SEPTA. "Railroad Substation Program" (PDF). Proposed Capital Plan: "Catching Up". Southeastern Pennsylvania Transportation Authority. Retrieved 31 December 2013.
  10. ^ "Bids | Page | SEPTA".
  11. ^ "Bids | Page | SEPTA".
  12. ^ "Carr and Duff, Inc". Carr & Duff.
  13. ^ http://www.septa.org/business/bid/results/detail/pdf/r14-156-JAB.pdf [bare URL PDF]
  14. ^ Almeida, John P. (November 20, 2016). "SEPTA Lansdale Parking Garage Lansdale PA November 19 2016 [6th photo and caption]". Railfan Pictures of the Week. The Philadelphia Chapter of the National Railway Historical Society. Retrieved 30 November 2016.
  15. ^ Almeida, John P. (June 21, 2015). "Out with the old: SEPTA transformer replacement Doylestown PA April 12 2015". Railfan Pictures of the Week. The Philadelphia Chapter of the National Railway Historical Society. Retrieved 29 June 2015.
  16. ^ a b "SEPTA Projects Funded Under Senate Bill 1" (PDF). PennDOT Decade of Investment. Pennsylvania Department of Transportation. Retrieved 31 December 2013.
  17. ^ SEPTA (November 2014). "A&E Services for Rehabilitation of Regional Railroad Division Substations (Proposal Number 14-268-JHC)". www.SEPTA.org. Retrieved 5 August 2015.

Rebuilding for the Future (Substation Program)

  1. ^ SEPTA. "Wayne Junction Static Frequency Converters (Main Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  2. ^ a b SEPTA. "Woodbourne Substation (West Trenton Line)". Rebuilding for the Future. Southeastern Pennsylvania Transportation Authority. Retrieved 29 June 2015.
  3. ^ SEPTA. "Ambler Substation (Lansdale/Doylestown Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  4. ^ SEPTA. "Bethayres Substation (West Trenton Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  5. ^ SEPTA. "Chestnut Hill East Substation (Chestnut Hill East Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  6. ^ SEPTA. "Doylestown Substation". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  7. ^ SEPTA. "Hatboro Substation (Warminster Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  8. ^ SEPTA. "Jenkintown Substation (Main Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  9. ^ SEPTA. "Lansdale Substation (Lansdale/Doylestown Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  10. ^ SEPTA. "Neshaminy Substation (West Trenton Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.
  11. ^ SEPTA. "Yardley Substation (West Trenton Regional Rail Line)". Rebuilding for the Future (Substation Program). Southeastern Pennsylvania Transportation Authority. Retrieved 5 August 2015.

References

  • Doub, C.L. (March 1931). "Power Supply Facilities for Reading Suburban Electrification". Transactions of the American Institute of Electrical Engineers. 50 (1). Institute of Electrical and Electronics Engineers (IEEE): 240–245.
    S2CID 51646983
    .