Garigliano Nuclear Power Plant

Coordinates: 41°15′31″N 13°50′06″E / 41.25849°N 13.83492°E / 41.25849; 13.83492
Source: Wikipedia, the free encyclopedia.
Garigliano Nuclear Power Plant
Garigliano Nuclear Power Plant in 1970
Map
Country
  • Italy
Coordinates41°15′31″N 13°50′06″E / 41.25849°N 13.83492°E / 41.25849; 13.83492
StatusBeing decommissioned
Commission dateJanuary 1, 1964
Decommission dateMarch 1, 1982
Operator(s)
Nuclear power station
Reactor typeBWR
Power generation
Units decommissioned1 × 150 MW
MW
External links
CommonsRelated media on Commons
]

Garigliano Nuclear Power Plant was a nuclear power plant located at Sessa Aurunca (Campania), in southern Italy. It was named after the river Garigliano.

Consisting of one 150MWe

Dresden Nuclear Power Plant
unit 1.

Final shutdown was on 1 March 1982 and the plant was handed to the Italian nuclear decommissioning authority SOGIN on 1 November 1999.[1] Decommissioning is expected to take 27 years, with the total bill expected to reach $432.4 million.[2]

History

The plant was built from November 1, 1959 to January 1, 1964 by Società Elettronucleare Nazionale.
On the 1st of June, 1964, the plant began the production of energy for commercial use. In 1965

ENEL
took property of the structure officially.
In 1978 the reactor was shut down and the production of energy ceased. The reactor was officially switched off on the 1st of March, 1982. During its lifetime the plant has produced 12,5 billion kWh of electric energy.
In 1987 some of the spent fuel rods were sent to Sellafield, England, to be reprocessed. The remaining fuel rods were kept in storage in Deposito Avogadro and in 2011 sent to La Hauge, France to be reprocessed also.
In 1999 the property of the plant was transfered to SOGIN, which began to dismantle the plant: the decomissioning is set to end in 2026.
Once reached the brown field status in 2026, the sphere and part of the structure will become a museum, in context of industrial archeology.
Instead the radioactive waste will remain on-site until its removal for permanent storage, and the deposits will be demolished.

Decommissioning

Installation of the new water treatment system (radwaste)

Because of the need to treat liquid waste produced during the dismantling , between 2014 and 2021 SOGIN built a new radwaste to replace the old one which was used during the plant's operating life.
In 2023 the new radwaste was used to treat the radioactive mud stored in tanks of the old radwaste system ( tanks T12, T13 and T26).[3]

Clean-up of trenches

During the late 1960s the burial of very low-level radiactive waste produced by the plant (such as contaminated protective clothing) was authorized. Three trenches were filled with waste.
In 2014 began the remediation of trench 2 and trench 3. In 2017 the reclamation of trench 1 started also. The clean-up ended in 2021.
All of the waste was then moved to the temporary deposit named D1. [4][5]

Dismantling of the central chimney

The old chimney in 1970

Sogin began dismantling the 95-meters-high (312 feet) concrete chimney in March 2014. First the structure had been decontaminated, then it was completely demolished in November 2017.[6] The old chimney has now been replaced with a new 34-meter-high (112 feet) steel chimney.

Dismantling of the water tower

The 72-meters-high (236 feet) water tower in 1970

On October 30, 2023, the works to dismantle the old water tower begun.[7]
The dismantling was completed on February 4, 2024. 1900 metric tons of non-radioactive material (2094 US tons) were produced due of the demolition, later sent to be recycled.[8][9]

Dismantling of the systems of the turbine hall

Still uncompleted.

Dismantling of the reactor

Still uncompleted.

On-site radioactive waste storage

Because of the increasing amount of waste generated due the decommissioning, two on-site deposits, realized between 2007 and 2013, were allocated to the mid-term storage of radioactive waste, waiting for its definitive storage in the National Repository of Radioactive Waste (which it hasn't been built yet).

  • Temporary deposit ex-diesel: the former emergency building that used to contain the diesel generators of the nuclear plant, now it stores 957 cubic meters of waste.[10]Maximum capacity: 960 cubic meters.
  • Temporay deposit D1: it stores 424 cubic meters of waste. Maximum capacity: 1100 cubic meters.

A third temporary deposit, named D2, is now being built and it is going to be finished in 2025.[11]
Some radioactive waste is being kept in steel drums outside the plant, waiting to be stored in the deposits.

Garigliano's total amount of radioactive waste
Very low-level activity waste Low-level activity waste Mid-level activity waste High-level activity waste
Cubic meters 1273 1138 85 0

The total amount was 2406 cubic meters in 2022.[12]

References

External links