Kakatiya Thermal Power Station
Kakatiya Thermal Power Project at Bhupalpalle | |
---|---|
Official name | KTPP |
Country |
|
Location | TSGENCO) |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Units operational | 1X500 MW 'Under implementation' 1X600 |
Nameplate capacity | 500 MW 'Under implementation' 600 MW |
Kakatiya Thermal Power Station is located near Chelpur village of
TSGENCO
Plant
This power plant was developed in 2 stages. The first stage comprised one 500MW unit. The unit was synchronized to grid with oil firing on 31.03.2010 at 06:08 hrs. Coal firing was immediately taken up and the load was raised up to 84 MW and the unit was in service with this load for about 1 hour.[1]
Kakatiya TPP Unit-II 1X600MW, was synchronized to the grid at 03:00 hrs. on 22 October 2015 and loaded to 105 MW.
Capacity
Stage | Unit Number | Installed Capacity (MW) | Date of Commissioning | Status |
---|---|---|---|---|
Stage I | 1 | 500 | May, 2010 | Running |
Stage II | 2 | 600 | Jan, 2016 | Running |
See also
- List of Power Stations in Telangana
References
- ^ "Kakatiya Thermal Power Station" (PDF). Central Electricity Authority. Archived from the original (PDF) on 26 September 2010. Retrieved 26 August 2010.
- ^ "BHEL commissions 600 MW Thermal Unit in Telangana | Central Chronicle". www.centralchronicle.com. Archived from the original on 25 April 2018. Retrieved 30 May 2017.