Masinga Hydroelectric Power Station

Coordinates: 00°53′21″S 37°35′40″E / 0.88917°S 37.59444°E / -0.88917; 37.59444
Source: Wikipedia, the free encyclopedia.
Masinga Hydroelectric Power Station
Annual generation
129 - 232 GWh

Masinga Hydroelectric Power Station, also Masinga Dam, is an

Seven Forks Scheme.[3]

Dam

Masinga Dam is a 60 m tall and 2,200 m long embankment dam[3] with a volume of 4,950,000 m³. The dam contains a spillway and a bottom outlet.[2]

Reservoir

At full reservoir level (maximum flood level of 1,056.5 m)

MW.[6]

Because of its large volume, the reservoir is crucial in regulating the flow of water for the other 4 hydroelectric power plants downstream.[7]

Power plant

The

GWh,[3]
depending on the water flow of the Tana River.

The power plant contains 2

ABB. The maximum hydraulic head is 49 m, maximum flow per turbine is 45.9 (45)[2] m³/s.[3]

History

Capital cost of the dam was US$172 million.[citation needed]

Feasibility studies were made in the 1970s and they confirmed the viability of a cascade of hydroelectric power plants along the Tana River: Masinga, Kamburu, Gitaru, Kindaruma, Kiambere, Karura, Mutonga, Low Grand Falls, Usheni, Adamsons Falls, and Kora. Only the first five of them have been built so far.[7]

Plans to raise the dam by 1.5 m in order to increase the volume of the reservoir up to 2 billion m³ were finally cancelled. The cost would have been US$15 million.[4]

In February 2018, KenGen resurrected plans to raise the Masinga Dam wall by 2 metres (6.6 ft), and install pumping equipment to recycle the downstream water discharge back to the dam for steady electricity output though the dry seasons. The

EDF Group, a French company to carry out the study.[8]

Heavy rains beginning in March 2018 led to major flooding throughout the Tana River area. On 17 May 2018, it was announced that the Masinga dam had reached capacity and had begun to overflow one week after the deadly failure of a smaller embankment dam in Solai. While safeguards in place prevented the dam from failing, other dams downstream had already reached capacity and authorities advised the evacuation of the towns of Garissa, Garsen, Hola, and Bura.[9]

See also

References

  1. ^ Globefeed.com (19 February 2018). "Distance between Nairobi Central, Nairobi, Kenya and Masinga Dam, Kenya". Globefeed.com. Retrieved 19 February 2018.
  2. ^ a b c "Masinga Dam". Salini Impregilo. Retrieved 2015-02-15.
  3. ^ a b c d e "Masinga Hydroelectric Power Station Kenya". Global Energy Observatory. Retrieved 2015-02-19.
  4. ^ a b c d Victor Juma (2013-02-26). "KenGen's bid to raise Masinga dam height suspended". Business Daily. Retrieved 2015-02-15.
  5. ^ "Tana and Athi rivers Development Authority".
  6. ^ Rob Jillo (2009-06-30). "KenGen closes Masinga Dam". Business&Tech. Retrieved 2015-02-15.
  7. ^ a b "MASINGA POWER STATION". Kenya Electricity Generating Company. Archived from the original on 2016-03-09. Retrieved 2015-02-19.
  8. ^ Otuki, Neville (19 February 2018). "KenGen signs fresh deal to upgrade Masinga dam wall". Business Daily Africa. Nairobi. Retrieved 19 February 2018.
  9. ^ Okuoro, Sara (17 May 2018). "Masinga Dam overflows". The Standard. Retrieved 18 May 2018.