Carrington Power Station

Coordinates: 53°26′09″N 2°24′39″W / 53.435771°N 2.410892°W / 53.435771; -2.410892
Source: Wikipedia, the free encyclopedia.

Carrington Power Station
Map
CountryEngland
LocationGreater Manchester, North West England
Coordinates53°26′09″N 2°24′39″W / 53.435771°N 2.410892°W / 53.435771; -2.410892
StatusOperational
Construction began
  • 2009
Commission date
    • 1956 (coal)
    • 2016 (gas)
Decommission date1991 (coal)
Operator(s)
Combined cycle
?
Yes
Power generation
Units operational2 (combined cycle gas)
Units planned4 × 60 MW
Units decommissioned4 (coal)
Nameplate capacity
  • 884 MW
  • 884 MW

grid reference SJ728933

Carrington Power Station is a

combined cycle gas turbine power station, which was completed in Autumn 2016 and began commercial operation on 18 September 2016.[1] It is located on the site of a former coal-fired power station, close to the villages of Carrington and Partington in the Greater Manchester Area and 12 km (7.5 mi) southwest of Manchester City Centre. The Manchester Ship Canal and the River Mersey run alongside the site, in Trafford, Greater Manchester, in North West England
.

History - coal-fired power station

Background

The station's site, on the south-east bank of the point where the

megawatts (MW), a total capacity of 480 MW over the site, but only the A station was built.[2]

Construction, design and specification

Because the station's site was surrounded by water on two sides, its

cills were made from artificial stone. The station had granolithic flooring, but the turbine hall and boiler room floors were tiled. The roofs were made from reinforced concrete with glass glazing. Two elevators were provided, to give access to all floors. The station's two chimneys were each 350 feet (110 m) high and of brick construction.[2] Ten million bricks were used in the construction of the station.[3]

Commissioning of the station's first generating set took place in 1953. All of the station's generating sets were commissioned by 1956.

in 1957.

Operation

The station generated electricity using four 60 megawatt (MW)

turbo-alternators, giving the station a total generating capacity of 240 MW. Steam for the generators was provided by seven boilers. Boilers no. 1 to 4 were produced by Babcock & Wilcox, and boilers no. 5 to 7 by John Brown Land Boilers. The latter were the first made by this company to be commissioned by the Central Electricity Authority.[2] The boilers had a rated output of 45 kg/s; steam conditions were 62.06 bar and 482 °C.[5]

Initially the station operated at base load, and maintained a good load factor into the middle of its life.

The generating capacity and electricity output from Carrington power station is given in the following table.[5][6][7][8]

Carrington generating capacity and output
Year 1954 1955 1956 1957 1958 1961 1962 1963 1967 1972 1979 1982 1989
Installed capacity, MW 56 112 168 244 240 256 256 256 240 256 256 256 240
Electricity output, GWh 118.191 687.620 816.664 1048.611 1699.250 1242.6 1227.1 1528.8 1743.4 1063.129 879.846 712.120 ?

The electricity output is demonstrated by the following graph.