Manuyo Uno station

Source: Wikipedia, the free encyclopedia.

Manuyo Uno
Line 1

Manuyo Uno station is an optional proposed stop on the

C-5 Extension in Las Piñas
.

Line 1 plan calls for an almost entirely elevated extension of approximately 11.7 km. The extension will have 8 passenger stations, with an option for 2 future stations (Manuyo Uno and Talaba), all intended to be constructed above-ground.[1]

The station is named after its proposed location in Barangay Manuyo Uno along C-5 Extension in Las Piñas.[1] It is one of two proposed Line 1 stations in Las Piñas and the other being Las Piñas station.

As of December 2021, the project is 61.60% complete. The extension is slated for partial operations by late 2024 or early 2025 and full operations by second quarter of 2027.

See also

References

  1. ^ a b "Project Update: The LRT Line 1 South Extension Project". Light Rail Transit Authority. Archived from the original on April 30, 2006. Retrieved March 25, 2012.