Maple Ridge Wind Farm
Maple Ridge Wind Farm | |
---|---|
Country |
|
Location | Lewis County, New York |
Coordinates | 43°47′07″N 75°34′31″W / 43.78528°N 75.57528°W |
Status | Operational |
Construction began | 2005 |
Commission date | June 2006 |
Owner(s) | Avangrid Renewables, EDP Renewables North America |
Wind farm | |
Type | Onshore |
Power generation | |
Units operational | 195 turbines |
Make and model | GW·h |
External links | |
Website | mapleridgewindfarm |
] |
Maple Ridge Wind Farm is the largest
Description
Maple Ridge Wind Farm, which achieved full operation in 2006, is a facility with 195 Vestas model V82 1.65 MW wind turbines. The Danish model machines were shipped in parts by sea to the United States,[1][3] and via the St. Lawrence Seaway to Lake Ontario, where they were unloaded at the Oswego Port Authority. They were transported by numerous trucks to the area of the farm near Lowville, New York.
Each turbine tower is 260 feet (79 m) tall. Each turbine has blades 130 feet (40 m) long, which added to the hub diameter gives a rotor diameter of 270 feet (82 m). Collectively, the turbines can produce a maximum of nearly 322 MW.[2]
Maple Ridge Wind Farm became fully operational in June 2006.[4]
The wind farm is located on Tug Hill in Lewis County, New York. The site was chosen because it lies at an elevation of 1,600–1,800 feet (490–550 m); strong winds are part of the area's lake-effect weather patterns generated by nearby Lake Ontario.
Maple Ridge Wind Farm was named in honor of Lewis County's maple syrup production, for which it ranks as the top county in New York.[2] The company generally leased a total of 21,000 acres (85 km2) of land for its facility, in an area used primarily as pasture and for the cultivation of feed-crops. NPR reported mixed reactions among the neighbors to the wind farm operations.[5][6]
Electricity production
Year | Total Annual MW·h
|
---|---|
2005 | 2,550 |
2006 | 543,936 |
2007 | 707,797 |
2008 | 751,386 |
2009 | 718,696 |
2010 | 701,519 |
2011 | 750,174 |
2012 | 723,940 |
2013 | 751,393 |
2014 | 813,135 |
2015 | 783,219 |
2016 | 764,322 |
2017 | 786,732 |
2018 | 739,631 |
Average (2007–2018) ---> | 749,329 |
See also
References
- ^ a b "Major US order for Vestas Wind Systems". Ministry of Foreign Affairs (Denmark). 2005-04-07. Archived from the original on October 17, 2006. Retrieved 2008-09-07.
- ^ Iberdrola Renewables. Retrieved 2014-02-06.
- Horizon Wind Energy. Archived from the originalon 2008-09-12. Retrieved 2008-09-07.
- Iberdrola Renewables. Retrieved 2014-02-06.
- ^ David Baron. "Wind Farm Buffets Family, Town Relations". NPR. Retrieved 2008-04-09.
- ^ "Wind Tour". New York State Assembly. Archived from the original on 2011-06-05. Retrieved 2008-09-07.
- ^ "Maple Ridge, Annual". Electricity Data Browser. Energy Information Administration. Retrieved April 14, 2019.
External links
- Building the Maple Ridge Wind Farm, Photographs of the turbines being off loaded at the Oswego Port Authority & shipped to Lowville.
- Wind Farm in My Backyard: ScienCentral Report
- A video showing wiring the turbines by International Brotherhood of Electrical Workers members
- Tapping Maple Ridge, documentary film about Maple Ridge Wind Farm
- Maple Ridge Wind Farm Fact Sheet