Paulo Afonso Hydroelectric Complex

Coordinates: 9°23′49″S 38°12′08″W / 9.39694°S 38.20222°W / -9.39694; -38.20222
Source: Wikipedia, the free encyclopedia.
Paulo Afonso Hydroelectric Complex
Hydroelectric
Power generation
Units operational23
Nameplate capacity4,279.6 MW (5,739,000 hp)
External links
CommonsRelated media on Commons

The Paulo Afonso Hydroelectric Complex (Complexo Hidrelétrico de Paulo Afonso), also known as the Paulo Afonso Complex, is a system of three

power plants on the São Francisco River near the city of Paulo Afonso in Bahia, Brazil. The complex exploits an 80-metre (260 ft) natural gap on the river, known as the Paulo Afonso Falls. Constructed in succession between 1948 and 1979, the dams support the Paulo Afonso I, II, III, IV and Apollonius Sales (Moxotó) power plants which contain a total of 23 generators with an installed capacity of 4,279.6 megawatts (5,739,000 hp).[1]

PA I was the first large power plant constructed in Brazil and the complex constitutes the densest area of dams in Brazil.[2][3] The complex provides electricity to areas in northeastern Brazil and is the main tourist attraction in the region.[4]

Background and history

On January 23, 1913, the 1.1 MW Angiquinho Hydroelectric Plant, built by

João Café Filho inaugurated PA I.[3] Previously, in 1953, CHESF negotiated with the government for a third generating unit at PA I and the excavation of another underground power plant for the future PA II adjacent to PA I on the falls.[3] The third generator at PA I was commissioned on September 18, 1955, and construction of PA II began that year as well.[6]

By 1961, PA II was complete and on October 24 that year, its first generator was commissioned. PA II's five other generators became operational between 1962 and December 18, 1967.[7] Construction on PA III started soon after in 1967 and was complete in 1971 with its first generator commissioned on October 21 that year. Another generator was commissioned in 1972 and the final two in 1974, the last of which on August 5.[8] In 1971, construction had moved to the Apollonius Sales (Moxotó) Dam and power plant 4 kilometres (2.5 mi) upstream from the falls. In 1977, construction was completed and its four generators went online in April of that year.[9] In 1972, construction began on the final dam and power plant, PA IV, 2 kilometres (1.2 mi) southwest of the falls. Construction was complete in 1979 and its first generator commissioned on December 1. Two more generators were commissioned in 1980, two in 1981 and the final on May 28, 1983.[10]

Construction of the dams caused a loss of 1,600 hectares (4,000 acres) of land along with displacing 52,000 people.[11]

Specifications

Apolônio Sales (Moxotó)

The Apolônio Sales Dam and power plant were originally known as Moxotó but were renamed after Apolônio Sales, the founder of CHESF.

generators, each with Kaplan turbines. Each generator has a nameplate capacity of 100 megawatts (130,000 hp) for a total installed capacity of 400 megawatts (540,000 hp).[9]

Paulo Afonso I, II, III

Overhead of the complex, click to expand
Generator hall of PA II

Situated directly on top of the Paulo Afonso Falls, the Delmiro Gouveia Dam supports Paulo Afonso I, II and III. The dam is 20 metres (66 ft) high, 4,707 metres (15,443 ft) long and is a concrete gravity type. The reservoir formed by the dam has a 26,000,000 cubic metres (21,000 acre⋅ft) capacity and surface area of 4.8 square kilometres (1.9 sq mi). The dam has one uncontrolled spillway and a controlled spillway on its outer linings while also supporting four controlled spillways on the front of the falls.[6] These four surface spillways when open, discharge water below and essentially recreate the falls.[4]

All three power plants are about 82 metres (269 ft) underground and adjacent to one another. PA I lies in the center and is housed in a 60-metre (200 ft) long, 31-metre (102 ft) high and 15-metre (49 ft) wide cavern. It contains three 60 megawatts (80,000 hp) generators with

Westinghouse. The turbines were manufactured by Dominion Engineering Works.[6] PA II is a 104-metre (341 ft) long, 36-metre (118 ft) high and 18-metre (59 ft) wide power house. It contains six Vertical Sync-type generators with Francis turbines. Two of the generators are 70 megawatts (94,000 hp), one is 75 megawatts (101,000 hp) and the remaining three are 176 megawatts (236,000 hp), for a total installing capacity of 443 megawatts (594,000 hp) MW. The generators were manufactured by S. Morgan Smith and Hitachi while the turbines by Voith.[7] PA III's power house is 127 metres (417 ft) long, 46 metres (151 ft) high and 18 metres (59 ft) wide. It contains four 198.55 megawatts (266,260 hp) Vertical Sync-type generators manufactured by Siemens for an installed capacity of 795.2 megawatts (1,066,400 hp). Each generator utilizes a Francis turbine manufactured by Voith.[8]

Paulo Afonso IV

The Paulo Afonso Dam located 2 kilometres (1.2 mi) southwest of the falls is 35 metres (115 ft) high and 7,430 metres (24,380 ft) long. The dam is an earth and rock-fill type but is 1,053 metres (3,455 ft) in length of concrete structures which include the power plant's intake and the spillway. The spillway is composed of eight floodgates and has a maximum discharge capacity of 10,000 cubic metres per second (350,000 cu ft/s). The dam withholds a 127,500,000 cubic metres (103,400 acre⋅ft) capacity reservoir with a surface area of 12.9 kilometres (8.0 mi). The reservoir receives water through a channel that originates near the southern end of the Appolonius Sales Reservoir and continues south, skirting the city. The PA IV power house is also underground and is 210 metres (690 ft) long, 52 metres (171 ft) high and 24 metres (79 ft) wide. It contains six 410.4 megawatts (550,400 hp) MW generators for an installed capacity of 2,462.4 megawatts (3,302,100 hp). Each generator is a SíncronoVertical-type manufactured by Siemens and utilizes vertical shaft Francis turbines that were manufactured by Voith.[10]

See also

References

  1. CHESF. Archived from the original
    on 6 July 2011. Retrieved 10 September 2010.
  2. ^ Campos Ferreira, Omar (June 2002). "The Brazilian Electric System". Economy & Energy. Retrieved 10 September 2010.
  3. ^ a b c d Muccini, Sandra (August 2007). "UMA CONTRIBUIÇÃO À HISTORIOGRAFIA DE BASE LOCAL E" (PDF). Rios Eletrônica – Revista Científica da FASETE (in Portuguese). 1 (1). Archived from the original (PDF) on 2012-03-12.
  4. ^ a b Cabral, Paulo (July 3, 2003). "Blogging in Brazil: Day nine". BBC News. Retrieved 10 September 2010.
  5. ^ "About the Flag of Paulo Afonso". CRW Flags. Retrieved 10 September 2010.
  6. ^
    CHESF. Archived from the original
    on 23 November 2015. Retrieved 10 September 2010.
  7. ^
    CHESF. Archived from the original
    on 24 November 2015. Retrieved 10 September 2010.
  8. ^
    CHESF. Archived from the original
    on 10 December 2015. Retrieved 10 September 2010.
  9. ^
    CHESF. Archived from the original
    on 23 November 2015. Retrieved 10 September 2010.
  10. ^
    CHESF. Archived from the original
    on 23 November 2015. Retrieved 10 September 2010.
  11. ^ Cernea, Michael M. "Hydropower Dams and Social Impacts: A Sociological Perspective" (PDF). World Bank. Retrieved 10 September 2010.
  12. ^ Fernandes, Adriana (December 16, 2005). "Hydroelectric power plants are built into the vegetation". Ecotourism. Archived from the original on 7 July 2012. Retrieved 10 September 2010.

External links