SBB-CFF-FFS Ce 6/8 I
This article includes a improve this article by introducing more precise citations. (August 2016) ) |
Ce 6/8I 14201 | |
---|---|
Verkehrshaus der Schweiz |
The Ce 6/8 I 14201 was one of four test locomotives ordered by the
History
In November 1913 the executive board of the
progressively forced the SBB to reduce schedules to the point where, in the autumn of 1918, only milk trains ran on Sundays. In response, the SBB hastened the electrification of the Gotthard railway line, among other important lines. This electrification was completed in 1920. For the traction on those lines, the SBB urgently needed passenger and freight locomotives.Requirement specifications
The SBB put forward the following requirements:
- Weight per running meter of maximum 7 t/m
- Maximum axle load of 18 t, later increased to 20 t after infrastructure upgrades
- Ability to haul 430 t up a 26 ‰ grade at 35 km/h
- Reliable run-up with this load up a 26 ‰ grade and acceleration to 35 km/h within 4 minutes
- Two trips from Arth-Goldau to Chiasso and back (780 km) within 28 hours
- Electrical brake for deceleration of the locomotive weight at slopes
- Ability to run at 20% overload for 15 minutes without damage
Commissioning and proposal
The contract was awarded as follows:
- BBC: Design and construction of the freight locomotive
Schweizerische Lokomotiv- und Maschinenfabrik (SLM): Mechanical part.
Beside the compliance with the requirements specifications the designers got big freedom in the work out of their designs.
Delivery date
The locomotive was delivered at 7 July 1919. The scheduled services started only in December 1919 (nota bene one week after the first
Technical details
The mechanical part
Running gear
The running gear consisted of two bogies. In both bogies three drive-axles and a jackshaft were installed. The center drive-wheel had a side play of 2×25 mm. At the outer side of each bogie an idle-axle was mounted. This idle-axle was designed as an Adams axle and had a side-play of 2×31 mm relative to the bogie. Small cabinets were mounted on the outer part of the bogie frames.
Transmission of tractive force
The tractive force was transmitted from the drive-axles to the bogies. From there the force was carried over to the bogie-mounted towing hook and the buffers. In between the bogies were connected with a spring-loaded coupling similar to the tender coupling at steam locomotives. The locomotive body was not engaged in the transmission of tractive force.
Drive
Two motors were mounted in each bogie frame. They were located between the second and third drive-axle. The motors drove big cogwheels in the
Locomotive body
The locomotive body consisted of single bridging slab. On this slab the body parts were fixed with screws. The bridging slab laid on the bogies using pivot bearings. To prevent the transmission of tractive forces over the body the bearings had longitudinal play. Beside these two spring-loaded bearings were mounted. The locomotive body was almost identical to the one of the Be 4/6 12302.
Braking equipment
The automatic Westinghouse air brake and the locomotive brake acted in both bogies to both sides of the driving wheels of each drive-axle. The idle-wheels did not have brakes. Each cab was equipped with a handbrake which acted to the respective bogie.
Electrical part
Primary circuit
Two
The cooling of the oil of the transformer occurred over a tube systems on both sides of the locomotive body by the use of an oil pump. These tubes were cooled by the air flow and the fan apertures in the body behind the tubes. These tubes were the main part of the very distinctive appearance of the locomotive as the Be 4/6 12302 and their successors Be 4/6 12303-12342.
The
Auxiliary systems
The subsequent listed auxiliary systems were fed from the lowest tap of the transformer over a main fuse:
- two compressors
- one motor-generatorfor battery charging
- cab heating
- foot heating plate
- fan groups for the motors
- one oil pump for the circulation of the transformer cooling oil
- oil heating plate in cab I
The train heating system was powered directly from the transformer with 1000 V over an electro-pneumatical hopper.
The control and lighting circuits were fed from the batteries with 36 V DC. The motor-generator for battery charging was mounted in the cabinet II.
Electrical brake
The locomotive was designed first with six drive-axles. Because of the weight limit it was not possible to install an electrical brake. However, for the long steep slopes such a brake would have been beneficial.
But shortly after the first runs a
The principle was as follows: A rotating phase converter fed the stators of the motors. In this way the activated rotors fed back the current through the transformer to the catenary.
The brake was extremely efficient. It was possible to hold 300 t at 26 ‰ in steady conditions. But the design was complicated and the operation was difficult. As a result, huge flashovers occurred from time to time. Several explosions in the main switch occurred too. Therefore, the equipment was removed in 1931.
Multiple-unit control
The locomotive was not equipped with a multiple-unit control.
Service
The Ce 6/8I started with scheduled services at December 1919. She led freight and commuter trains between Bern and Spiez.
20 January 1920 the SBB commissioned the locomotive. From March 1920 until October 1920 the
As Ce 6/8I 14201 it continued the scheduled service at 18 October 1920. The trips never went further than to Spiez. March 1921 the locomotive was relocated to the Gotthard.
The Ce 6/8I started its scheduled service almost at the same time as the first
At the beginning the locomotive started its services from the depot of
After the removal of the regenerative brake the locomotive returned 1931 to Erstfeld. 1938 it was relocated to the depot of Basle. There she was leading miscellaneous freight trains. The locomotive drivers did not like the quite poor running characteristics. On the other hand, they had to admit that they liked the high tractive force at lower speeds.
In 1961 two motors were damaged heavily. Since the EXPO 64 (Swiss National Exhibition/Schweizerische Landesausstellung) was very close it was decided to re-coil the defective motors. During this repairing action the locomotive was used in the Ticino canton. The two defective motors were replaced by ballast weights. Subsequently, the two motors were mounted again and the two others were revised.
After this action the performance of the locomotive was still very remarkable:
- 1963: 101,000 km
- 1964 (EXPO-Jahr): 65,000 km
Later the performance decreased rapidly:
- 1965: 19,000 km
- 1966: 4,000 km
At the end of its career the locomotive was used up to 1982 test locomotive for brake tests. It was then handed over to the
References
- Schneeberger, Hans (1995). Die elektrischen und Dieseltriebfahrzeuge der SBB, Band I: Baujahre 1904–1955 (in German). Luzern: Minirex AG. ISBN 3-907014-07-3.[page needed]
- Jeanmaire, Claude. Die elektrischen und Diesel-Triebfahrzeuge schweizerischer Eisenbahnen, Die Lokomotiven der Schweizerischen Bundesbahnen (SBB) (in German). ISBN 3-85649-036-1.[page needed]