Blackburn Meadows
Blackburn Meadows | |
---|---|
Type | Waste Water Treatment Works |
Location | Sheffield, South Yorkshire, England |
Coordinates | 53°25′20″N 1°23′35″W / 53.42222°N 1.39306°W |
Created | 1886 |
Operated by | Yorkshire Water |
Blackburn Meadows is an area of land just inside the
The works had its own internal
A power station was operational on the southern part of the site from 1921, supplying electricity to the steel works of the Lower Don Valley. Although it closed in October 1980, two of its cooling towers which were designed by L. G. Mouchel and Partners in 1937, remained until 2008, as demolition was difficult because of their proximity to
Sewage Treatment Works
Blackburn Meadows is the lowest point within
History
As the population of Sheffield increased, Sheffield Corporation bought 23 acres (9.3 ha) of land at Blackburn Meadows, on which to build a
By mid-1886, the works was complete, and the Mayor, J. W. Pye-Smith Esq, officially opened it on 2 June. The event was witnessed by members of the Council, and by invited guests, which included a representative from the
The railway also developed, with the acquisition of 250 yards (230 m) of portable track and six tipping wagons in 1889, a steam crane later the same year, and more wagons in 1891 and 1892. The first locomotive arrived in 1898, after its purchase from the
In parallel with the construction of the works, trunk sewers were built to convey sewage from the city to the works. These was a major programme of expansion to the sewer network in 1910, to ensure that it could cope with the expected volumes of effluent produced. Because British sewers are also expected to handle rainwater, a series of storm sewage overflows were provided, which resulted in diluted sewage being discharged into the River Don in times of heavy rainfall.[6]
Expansion
The quality of the effluent discharged into the Don was soon giving rise to concern, as the treatment process was unsatisfactory. An
The Lord Mayor opened the first part of the new works on 28 October 1909, and Sheffield Council increased the amount of land they owned for sewage treatment to 226.5 acres (91.7 ha) by buying another 81 acres (33 ha), on which contact beds could be constructed if required at a later date. Discharges to the river were still of poor quality, and a secondary treatment process was designed, although its implementation was delayed by the onset of the
In 1915, the Corporation had made enquiries about purchasing a second-hand steam engine, approaching six locomotive manufacturers, but eventually acquired a new 0-4-0 saddle tank from
Modernisation
The entire works was upgraded between 1956 and 1969, in five distinct phases. The plan was announced in January 1956, and was expected to cost £1 million. The first phase was the construction of a filter pressing plant, for which the main contractor was Norwest Construction Co Ltd, while the actual presses and other plant were supplied by S. H. Johnson and Co Ltd. This phase was completed in 1962, and was officially opened by the Lord Mayor on 14 May 1963. The second phase consisted of a preliminary treatment plant, a storm sewage separation plant, and metering of the flows within the plant. This was completed in 1965. The third phase was split into two parts, which initially involved the building of new primary sedimentation tanks. Once these were operational in 1969, the old sedimentation tanks were converted to become temporary storm sewage tanks. This fourth phase was called phase 3b, and was completed in 1970. The final phase was the construction of a sludge incinerator, which was completed in 1969 and meant that the pressed sewage cake did not have to be taken to Thrybergh to be dumped.[12]
The railway was also upgraded at this time. Thomas Ward Ltd supplied replacement track in 1955, and a new 0-4-0 diesel electric shunter was ordered from
In 1976, a new diesel shunting locomotive, made by
By the 1960s, the Sheffield sewers were inadequate for the volume of effluent, and overflowed into the river during periods of light rainfall and sometimes when there was no rainfall. Some of them had been in use for 80 years, and inspection revealed that major reconstruction was required. The solution adopted was to tunnel the Don Valley Interceptor Sewer through the Carboniferous rock beneath the existing sewers. Work began of the first phase in 1979, when 1.33 miles (2.14 km) of 18-foot (5.5 m) tunnel were built from the works to a drop shaft in Hawke Street. A new pumping station was required at Blackburn Meadows, and this phase was completed in July 1983. Over the next decade, four further phases were completed, involving the tunnelling of 1.39 miles (2.24 km) of sewer with a diameter of 12 feet (3.7 m) to a drop shaft near Furnival Road, a new sewer from Furnival Road to the Whitbread Brewery with another from the Sheaf Valley sewer to the central bus station, extension of the Don Valley sewer to Gilpin Street, and finally extension from Gilpin Street to Livesey Street in Hillsborough. As a result of this work, the capacity of the sewers was greatly increased, and 26 storm sewage overflows were closed, resulting in significant improvement to water quality in the river.[6]
Improvements
In 1992, the problem of ammonia levels in the final effluent was addressed by the construction of a system using anoxic zones and diffuse air activated sludge treatment. This dramatically reduced ammonia levels, and was the most significant factor in the re-establishment of fish stocks in the lower River Don.[9] In 1990, the outdated filter presshouse and incineration plant were replaced by a new sludge-dewatering plant and a fluidized-bed incinerator.[16] The new plant made the old sludge beds, situated to the east of the River Don and on the island formed by the Don and the Holmes Cut, redundant, and these have now become a nature reserve. Further improvements to the process were completed by 2005. These included an upgrade to the wet scrubbing system, in order to remove heavy metals and acid gases such as sulphur dioxide, hydrogen chloride and hydrogen fluoride from the flue gases produced by the incinerator, and the addition of a tertiary adsorption filter, which removes mercury and dioxins. The improvements were designed to ensure that the plant met the standards set out in the Waste Incineration Directive.[17]
The outflow from the works, which passes under the
The works was shut down on 25 June 2007, after the Don burst its banks, and the entire site was engulfed by several feet of water. It remained submerged for over a week, with much of the equipment suffering catastrophic damage. Once the water subsided, imaginative ways had to be found to return it to operation within a reasonable time. The analyser which measures emissions from the incinerator plant had been completely destroyed, and in order to mitigate a 16-week delivery time, the manufacturers removed one from a training centre at Telford, and it was hired by Yorkshire Water until a new unit could be supplied. The plant was recommissioned and operational just 18 days after its inundation.[20]
In 2012, a contract for the construction of a mesophilic anaerobic digestion facility was awarded, including the construction of buildings and various other pieces of equipment required for the treatment of sludge. Mesophilic anaerobic digestion enables the breaking down of biodegradable materials using micro-organisms under moderate temperatures. The new sludge treatment facility enables the recycled sludge to be used on neighbouring farmlands as manure, and also enables Yorkshire Water to generate 1.9MW of renewable energy using combined heat and power units.[21]
Association with biological warfare
In 1942 Olympia Oil and Cake Company (based in Blackburn Meadows) was outsourced to produce 5,273,400 cakes by the Porton Down biology department for use in Operation Vegetarian.[22]
Power Station
In 1921, Sheffield Corporation built a coal-fired power station on spare land at the south west corner of Blackburn Meadows. At the time there was no national grid, and the steelworks which occupied much of the Lower Don Valley needed additional electrical power. without damaging the motorway.
In 2011, as part of Sheffield City Council's drive to become self-sufficient for energy, construction of a biomass power station began. It is operated by E.ON UK, and was completed in 2014. It generates 30 megawatts by burning waste wood, sourced from the United Kingdom, and waste heat is captured to provide a district heating scheme.[27][28]
Nature Reserve
In 1993
Bibliography
- Abbott, Justin; Jones, Ken; Wright, Steve (April 2004). "Yorkshire Water's Sewage Sludge Incinerators" (PDF). Wastewater Treatment and Sewerage. Archived (PDF) from the original on 2 August 2016.
- Booth, A. J. (1986). Sheffield's Sewage Works Railways. Industrial Railway Society. OCLC 877087235.
- Firth, Christopher (1997). Domesday to the dawn of the New Millennium - 900 years of the Don fishery. Environment Agency. (This is available online at The Don Catchment Rivers Trust. Page numbers refer to the pdf file).
- Lima, R.; Bachmann, R. (2002). "Blackburn meadows wastewater treatment works". International Journal of Water. 2: 35. hdl:10198/1421.
- Tolan, D. J.; Bennett, D.; Kwiecinski, J. V. (June 1991). "Blackburn Meadows Sewage-Treatment Works: Sludge Incineration into the 1990s". Water and Environment Journal. 5 (3): 239–248. .
References
- ^ "Bench Marks". Ordnance Survey. Retrieved 6 November 2012. (Rivet at SK40999170)
- ^ a b Booth 1986, p. 1.
- ^ "My birthday treat-ment". The Star. 14 July 2006. Archived from the original on 25 September 2012. Retrieved 24 March 2011.
- ^ Booth 1986, pp. 1–2.
- ^ Booth 1986, p. 2–3.
- ^ a b Firth 1997, p. 52.
- ^ Booth 1986, pp. 3–5.
- ^ Booth 1986, p. 6.
- ^ a b Firth 1997, pp. 46–47.
- ^ Booth 1986, pp. 8–10.
- ^ Booth 1986, pp. 25–26.
- ^ Booth 1986, p. 10.
- ^ Booth 1986, pp. 10–16, 27.
- ^ Booth 1986, p. 18.
- ^ "Thomas Hill 'Vanguard' 4wDH Charlie". Andrew Briddon Locos. Archived from the original on 1 March 2012. Retrieved 24 March 2011.
- ^ Tolan, Bennett & Kwiecinski 1991.
- ^ Abbott, Jones & Wright 2004, pp. 37–39.
- ^ "Customers get value for money in Yorkshire". Yorkshire Water. Archived from the original on 14 March 2012. Retrieved 24 March 2011.
- ^ Lima & Bachmann 2002, p. 35.
- ^ "ABB Rises To Floods Challenge". ABB. Archived from the original on 19 March 2012. Retrieved 24 March 2011.
- ^ "Waste treatment sludge to fuel city's £23m green energy plant". Yorkshire Post. 23 April 2012. Archived from the original on 15 March 2021.
- ProQuest 331261246.
- ^ a b "Cooling Towers, Sheffield, Advisers Report" (PDF). English Heritage. 10 March 2008. Archived from the original (PDF) on 5 October 2011. Retrieved 24 March 2011.
- ^ Ordnance Survey, 1:2500 map, 1923 (available here)
- ^ "Robson Renewable Fuel Systems to be Installed in Sheffield". Geo Robson & Co. Archived from the original on 18 November 2013. Retrieved 7 December 2012.
- ^ "Echoes of Blackburn Meadows". BBC. 27 January 2010. Retrieved 24 March 2011.
- ^ "Plans for £120m Sheffield biomass power plant unveiled". BBC News. 14 November 2011. Retrieved 26 November 2016.
- ^ "Blackburn Meadows Renewable Energy CHP Plant". E.ON. Archived from the original on 12 November 2020. Retrieved 26 November 2016.
- ^ Curtis, David (27 May 2005). "Blackburn Meadows Nature Reserve". Sheffield City Council. Archived from the original on 12 June 2011. Retrieved 24 March 2011.