Cougar Dam

Coordinates: 44°7′44″N 122°14′25″W / 44.12889°N 122.24028°W / 44.12889; -122.24028
Source: Wikipedia, the free encyclopedia.
Cougar Dam
Aerial view
LocationLane County, Oregon, U.S.
Coordinates44°7′44″N 122°14′25″W / 44.12889°N 122.24028°W / 44.12889; -122.24028
Opening date1964[1]
Operator(s)Cenwp[1]
Dam and spillways
ImpoundsSouth Fork McKenzie River
Height519 feet (158 m)[1]
Length1,600 feet (488 m)[1]
Reservoir
CreatesCougar Reservoir
Total capacity219,000 acre-feet (0.270 km3)[1]
Catchment area210 square miles (544 km2)[1]
Surface area1,280 acres (520 ha)[1]

Cougar Dam is a 519-foot (158 m) tall rockfill hydroelectric dam in the U.S. state of Oregon. It has a gated concrete spillway and a powerhouse with two turbines totaling 25 megawatts of electric power.[2][3]

The dam impounds the

flood risk management, hydropower, water quality improvement, irrigation, fish and wildlife habitat, recreation, storage, and navigation.[3][4]

In 2005, the Willamette temperature control facility was constructed to help regulate the water temperature released to the river below Cougar Dam in an attempt to reduce the negative effects on salmon migration.[5] To further help recover threatened chinook salmon and bull trout populations,[6][7] in the Willamette River Basin, the U.S. Army Corps of Engineers constructed a fish collection and sorting facility on the South Fork McKenzie River below Cougar Dam which was completed in 2010.[5] From 2003 to 2005, state-of-the-art turbine runners were installed in the turbine-generator units at the Cougar powerhouse, and were designed to resist cavitation and operate efficiently at very large head ranges.[2]

Background

Cougar Dam was completed in 1963 at a cost of $54.2 million and the two turbine units were completed in 1964.

Blue River Dam to control flooding, and since the completion of the dam, it is estimated that it prevented approximately $452 million in potential flood damages.[3] The dam consists of a rock-fill embankment approximately 1,500 feet (460 m) long, a penstock to power two Kaplan turbines, an emergency spillway capable of a capacity of 76,140 cu ft/s (2,156 m3/s), a regulating outlet, and a diversion tunnel.[8] The diversion tunnel was built to divert the South Fork McKenzie River during the construction of Cougar Dam, and the tunnel was later closed with a concrete plug once the construction of the dam was complete.[8]

Temperature control tower

The original intakes for the powerhouse and regulating outlet were deep and pulled water from the bottom of the reservoir which is much colder than the surface water.[9] During the spring and summer, the release of unnaturally cold water into the McKenzie River reduces salmon migration and productivity.[9] In the fall, the reservoir level is considerably lower and the warmer water from the surface enters the intakes and makes the river downstream unnaturally warm which causes salmon eggs to hatch several months too early. In order to help control the temperature of water discharged below the dam, the original intake tower was modified by adding a 302-foot (92 m) tall wet well. The wet well has three adjustable gates at various levels so that different temperature water can be mixed in the wet well to a desired temperature.[9] The mixed water enters the existing regulating and penstock intakes.[8] By controlling the temperature of the water released from the dam, the impacts on the McKenzie River are greatly reduced.[9]

Fish collection and sorting facility

When the Cougar Dam was originally constructed, it contained adult and juvenile fish passage facilities that helped fish move past the dam. However, fish no longer migrated to the facility, and it became ineffective.[5] The Army Corps of Engineers decided to construct a new collection and sorting facility to collect, sort, and transport fish upstream and downstream of the dam. The new facility would cost $14.7 million and include a fish ladder, presort pool, sorting facility, and two pump structures for water supply.[10] At the collection and sorting facility, adult salmon and bull trout will be loaded on trucks and released into high-quality habitats above Cougar Dam in an effort to recover threatened salmon and bull trout populations.[5]

Replacement of turbines

The runners from the two turbines in the Cougar powerhouse experienced significant cavitation damage during operation and by the 1980s they were in need of repair and had to be taken out of service four times a year for inspections and repair.

Voith Siemens Hydro Power Generation.[2] By 2000, the replacement runners were again experiencing cavitation problems and in need of repair. Repair of the runners would prove to be difficult because the runner blades are thin, making them difficult to weld, and the spacing between the blades is small which gives limited access to the damaged area. The U.S. Army Corps of Engineers realized that a state-of-the-art runner design was required and devised a turbine-generator rehabilitation program. Due to the technical challenges associated with the program, the Corps chose a best value procurement method for this project. In 2003, the contract was awarded to General Electric Hydro of Montreal, Quebec, Canada and the project was completed in March 2005. The project included physical model testing, new turbine runners, a major turbine overhaul, a generator
rewind, and disassembly and reassembly of the units. The problems with the runners for the turbines at Cougar powerhouse are associated with the cycle of large head changes of the Cougar Reservoir.[2] Since Cougar Reservoir is built for flood control, the levels of the reservoir vary greatly, causing the units to operate at heads between 400 and 438 feet (122 and 134 m) one third of the time and at heads between 270 and 310 feet (82 and 94 m) one fifth of the time.[2] In 2002, the Corps began lowering the level of the reservoir for the construction of a temperature control facility.[9] The reservoir level was lowered to an elevation below the turbine intakes, which put the powerhouse out of service and provided an opportunity to overhaul the turbine-generator units.[2]

See also

  • List of lakes in Oregon

References

  1. ^ a b c d e f g "Cougar Dam". National Performance of Dams Project Directory. Department of Civil and Environmental Engineering, Stanford University. Archived from the original on July 16, 2011. Retrieved May 9, 2011.
  2. ^ a b c d e f g h G. Charles Allen Jr., U.S. Army Corps of Engineers. "Seeking Best Value During Equipment Procurement". Hydro World. HCI Publications, Inc., a division of PennWell Corporation. Retrieved May 9, 2011.
  3. ^ a b c d e "Cougar Dam and Reservoir". Archived from the original on May 17, 2011. Retrieved May 9, 2011.
  4. ^ a b "Cougar Dam". Bonneville Power Administration. Archived from the original on July 26, 2011. Retrieved May 9, 2011.
  5. ^ a b c d "Corps Completes Cougar Dam Fish Collection Facility To Aid McKenzie River Salmon, Bull Trout". Columbia Basin Bulletin. Intermountain Communications. August 27, 2010. Archived from the original on October 8, 2011. Retrieved May 9, 2011.
  6. ^ "5-Year Review: Summary & Evaluation of Upper Willamette River Steelhead and Upper Willamette River Chinook" (PDF). National Oceanic and Atmospheric Administration. 2011. Retrieved 2013-12-03.
  7. ^ "Species Profile-Bull Trout (Salvelinus confluentus)". U.S. Fish and Wildlife Service. Retrieved 2013-12-05.
  8. ^ a b c Bird, Brad; Stephen J. Schlenker; Nathan T. Higa (October 8, 2003). "Design of a Multi-Level Intake for Temperature Control featuring a Lake Tap at Cougar Dam, Vida, Oregon" (PDF). U.S. Army Corps of Engineers. Archived from the original (PDF) on July 21, 2011. Retrieved May 9, 2011.
  9. ^ a b c d e "Cougar Reservoir Water Temperature Control and Upstream Passage Project". Oregon Department of Fish and Wildlife. Archived from the original on August 23, 2011. Retrieved May 9, 2011.
  10. ^ "The Projectwise Project Showcase". Bentley Systems. 2011. Retrieved May 9, 2011.