Route Trident
Route Trident (known locally as the New or Big Road)[1] was built by the British Army's Royal Engineers in Helmand Province, Afghanistan. The construction of the road was codenamed Operation Lar Jarowel by the Ministry of Defence.[2] Route Trident (named after the Regimental emblem of 28 Engineer Regiment—the Amphibious Engineers who have the Trident as their emblem) replaced an older road that was vulnerable to attack by insurgents on convoys supplying three patrol bases established in the Gholam Dastagir Kalay area as part of Operation Panther's Claw. In the immediate aftermath of operation the Light Dragoons Battlegroup were suffering casualties as they tried to secure the area and resupply their patrol bases. The attacks resulted in the deaths of two British servicemen and led to the cancellation of the convoys, forcing the bases to be resupplied by air.
Following a meeting between the Commanding Officer of the Light Dragoons (Lt Col Fair) and Commanding Officer of 28 Engineer Regiment (Lt Col MTG Bazeley) it was decided that a new and easier to protect road would be constructed by the Royal Engineers. 28 Engineer Regiment had used a
Background
Route Trident was constructed to connect three
During 2009 two British soldiers were killed and 17 injured while completing a resupplying patrol to Patrol Base 4. The land convoys were subsequently stopped and replaced by aerial resupply with helicopters and Hercules transport aircraft.[5] The use of aircraft used up valuable resources of the local British logistics system and the Coldstream Guards were often forced to fight to reach the air dropped supplies.[5][8] The British Army decided to construct a road to allow better resupply of their patrol bases, to stimulate local markets and social movement, to provide greater stability, and to facilitate reconstruction in the area.[5][9]
Design
The cost of construction aggregate in Afghanistan is high (around $250 to $650 per cubic metre) because of security and transport costs, therefore Foley attempted to minimise its use. A series of field trials using various
Construction
[The project was] a dream come true for a young engineer officer.
The construction of Route Trident was begun by the British Army during the second half of Op HERRIcK XI. The project manager appointed for the construction phase was
Construction began at Gholam Dasagir Kalay in mid-December 2009 and progressed to the neighbouring village of
Today marks the end of a large-scale engineering project, the first of its kind. All sappers who have worked on the project hope that it will bring enhanced security to both our own troops and local people in this part of Afghanistan.
Captain Dick Gale, project manager.[8]
The project encountered several problems not typically associated with road construction. Materials had to be brought in for the road from as far away as Kandahar, Quetta, in Pakistan, and the United Kingdom; and the work was carried out in 50 °C (122 °F) heat.[5][11] The design was altered as a result of consultations with local Afghans, who wanted, for example, to route the road through villages where possible, to minimise the loss of agricultural land.[11] The Taliban carried out direct attacks and used intimidation to deter workers; at least one was beaten and kidnapped.[7] Despite these difficulties the first supply convoy travelled along the road on 10 March 2010, completing a journey that took 36 hours on the old road in just 30 minutes. The road was officially declared completed on 12 March 2010, and another convoy made the trip that day in just 25 minutes.[10]
Impact
Where once there was an IED-infested dirt track there is now a line of communication which will stimulate trade and save lives.
Completion of the road meant that supply aircraft could be replaced by land convoys and reallocated to other areas.[5] In addition to its military benefit the road improved the local quality of life with shops, markets, a doctors surgery and a school being built alongside it.[10] There was also an improved sense of security for people in the area, and more patrols were able to move along the road. Such was the feeling that one building contractor felt safe enough to return to Babaji from Lashkargah to offer his services to construct a permanent vehicle checkpoint for the route.[6] The design and construction techniques used in the road were so successful that they are being rolled out to engineering projects across Helmand.[10]
Extension
There are plans to extend Route Trident north and south into the area secured by
As of 7 July 2010 the two construction battlegroups, working from each end of the new extension, were just 7 kilometres (4.3 mi) apart.[13] The work proved to be challenging, with a large number of culverts having to be installed and high levels of insurgent activity in the area. One local contractor refused to work because of security issues, which resulted in the project being delayed from its original finish date of July to October 2010.[16]
Responsibility for security of the road and its extension passed from the Coldstream Guards to the
By September there was said to be "steady progress" on the extension of the road with elements of 1 Troop of the 1st Armoured Engineer Squadron, 21 Engineer Regiment being brought in from Ripon, Yorkshire to assist.[20] Insurgent attacks had become an almost daily occurrence and halting work was said to be "the insurgents' main effort in [the] area".[20] Operation Oqab Jarawel (in English: Eagle's Build) was launched in October 2010 to provide security for the extension of the route over the Loy Mandeh river.[21] The operation involved elements of 2nd Battalion Royal Regiment of Scotland and the 2nd Royal Tank Regiment working alongside Afghan forces to clear three villages of insurgents and set up new checkpoints to secure the area.[21] The operation was highly successful, resulting in a 90% reduction in attacks in the area and allowing the new bridge to be built by the start of January 2011.[21]
By early October 2010 Route Elephant, which will link with Trident and runs from Highway 1 to Lashkargah, was said to be very successful with a sixfold increase in traffic.[22] As of mid-November 2010 Route Trident was still under construction.[23]
The Route Trident extension between Lashkargah and Grishk was reported as complete on April 15, 2011, and has cut journey times between the two centres from two weeks to just two-and-a-half hours and seen insurgent attacks drop by 90 per cent.[2]
References
- ^ Ministry of Defence (1 July 2010). "Gurkhas and ANA bring life back to the village of Piand Kalay". Retrieved 3 September 2010.
- ^ a b Ministry of Defence (15 April 2011). "Route Trident extension helps bring prosperity to Helmand". Retrieved 22 April 2011.
- ^ a b c d e f g h i "Road to Hearts & Minds". New Civil Engineer. 8 July 2010. p. 18.
- ^ a b c Ministry of Defence (19 March 2010). "Engineers complete secure route through Panther's Claw territory". Retrieved 3 September 2010.
- ^ a b c d e f g h i j k l m n Ministry of Defence (19 March 2010). "Engineers complete secure route through Panther's Claw territory". Retrieved 3 September 2010.
- ^ a b c Ministry of Defence (1 March 2010). "Provincial Update". Archived from the original on 16 July 2011. Retrieved 3 September 2010.
- ^ a b c d BBC News (28 January 2010). "Progress slow and messy in Afghanistan". Retrieved 3 September 2010.
- ^ a b British Army (22 March 2010). "Engineers pave the way to a brighter future in Helmand". Retrieved 3 September 2010.
- ^ British Army. "28 Engineer Regimental Group report by Lt Col MTG Bazeley". Retrieved 3 September 2010. [dead link]
- ^ a b c d e f "Road to Hearts & Minds". New Civil Engineer. 8 July 2010. p. 19.
- ^ a b c d BBC News (1 July 2010). "Leeds Soldier helps Route Trident through Afghanistan". Retrieved 3 September 2010.
- ^ Pannell, Ian (28 January 2010). "Progress slow and messy in Afghanistan". BBC News.
- ^ a b c Ministry of Defence (6 July 2010). "Gurkhas help Royal Engineers continue Babaji regeneration". Retrieved 3 September 2010.
- ^ Lydall, Ross (18 March 2010). "Woman soldier's team of engineers defy Taliban to tame fatal 'bomb alley'". London Evening Standard. Archived from the original on 14 May 2010. Retrieved 3 September 2010.
- ^ Ministry of Defence (3 February 2010). "28 Engineer Regiment are building bridges in Helmand". Retrieved 3 September 2010.
- ^ a b "Programmed for Peace". New Civil Engineer. 16 September 2010. p. 18.
- ^ "Gurkha patrols bring hope to troubled Afghan village". Kent Online. 23 June 2010. Retrieved 3 September 2010.
- ^ "Tributes paid to soldier". Yarmouth Mercury. 8 July 2010. Archived from the original on 12 July 2010. Retrieved 3 September 2010.
- ^ Ministry of Defence (23 July 2010). "Corporal Matthew James Stenton and Lance Corporal Stephen Daniel Monkhouse killed in Afghanistan". Retrieved 7 September 2010.
- ^ a b Ministry of Defence (15 September 2010). "Cavalry soldiers protect engineers building new Helmand road". Retrieved 4 December 2010.
- ^ a b c Ministry of Defence (4 January 2011). "British and Afghan operation sees villagers return". Retrieved 16 January 2011.
- ^ Ministry of Defence (7 October 2010). "Steady and significant progress in Helmand". Retrieved 4 December 2010.
- ^ "The week on Op Herrick 15 - 21 Nov 10". RAF Families Federation. Archived from the original on 16 July 2011. Retrieved 4 December 2010.
External links