DND–KMP Expressway

Source: Wikipedia, the free encyclopedia.

DND–KMP Expressway
(NH–148NA)
KMP, Khalilpur, Nuh district, Haryana
Location
Country
Ballabgarh, Sohna & Jewar
Highway system

The DND–Faridabad–KMP Expressway, formally known as NH-148NA is a 59

Jewar Airport.[3]

The DND/

NHAI for the construction of NH–148NA highway. The construction work was started in May 2021 and 20 Km stretch from KMP interchange to NH-2 interchange at Kail Gaon (Ballabhgarh
) has been opened on 12 February 2023. The entire project is expected to get completed by June 2024.

Route

The NH–148NA highway connects

Delhi-Mumbai Expressway via an interchange at Khalilpur, Nuh district (Haryana).[4][5]

NCT of Delhi (12 km)

Haryana (47 km)

KMP interchange

After reaching KMP interchange at Khalilpur, traffic coming from Maharani Bagh (Delhi) and Faridabad bypass has 2 options:

1. They can turn south towards Dausa and Mumbai, or turn north towards Gurgaon and Sohna.

2. They can also use

KMP Expressway and turn east for Palwal and turn west for Manesar
.

Construction

The construction work of the 'DND–Faridabad–KMP' section was awarded by the National Highways Authority of India (NHAI) to Dineshchandra R. Agrawal Infracon Private Limited (DRA Infracon) in August 2020.[7] This project will reduce congestion on Ashram to Ballabhgarh route (via Badarpur). In Haryana it will have multiple Flyovers and a 3-lane service road on either side of Faridabad bypass road.

7 km out of 9 km route of Package-1 in Delhi state will be elevated with two-level crossings at 4 locations of the Delhi Metro rail line (near Okhla Vihar and Kalindi Kunj metro station), making it the 1st expressway in India to cross above elevated metro rail line. NH-148NA exits Delhi at MCD Toll Plaza (near Mithapur) which is 12.5 km from the DND starting point.

Packages

The

km long DND–Faridabad–KMP section of Delhi–Mumbai Expressway project into three packages and awarded it to DRA Infracon. Its construction cost is around 5,332 crores (including land acquisition cost).[8][9]

Sr No Package Length in
km
Value in crores State
1. Junction of DND Flyway & Ring Road in Delhi to Jaitpur–Pushta road in Delhi 09
1,881
Delhi
2. Jaitpur–Pushta road in Delhi to Sector-62/65 dividing road in Faridabad 24
1,832
Delhi & Haryana
3. Sector-62/65 dividing road in Faridabad to KMP Expressway at Khalilpur in Nuh district 26
1,619
Haryana

Note:

Delhi–Mumbai Expressway

The construction work of

NHAI
into 4 sections with a total of 52 tenders/ construction packages as given below. The entire 1,350 km long expressway is expected to be completed by January 2024.

Section Length in
km
No. of packages State-wise packages
KMP
59 03 1 in Delhi and 2 in Haryana
KMP–Vadodara
844 31 3 in Haryana, 13 in Rajasthan, 9 in Madhya Pradesh and 6 in Gujarat
VadodaraVirar 354 13 10 in Gujarat and 3 in Maharashtra
JNPT
92 05 5 in Maharashtra

Jewar Airport link

The

NHAI
to Apco Infratech Pvt. Ltd. on 29 July 2022.

Spur Package Length in
km
Value in crores State
Faridabad bypass (Sector 65), via interchange with EPE at Mohna, to Yamuna Expressway at Dayanat Pur village, north of Jewar 31
1,660
Haryana and UP

Status updates

See also

References

  1. ^ "Faridabad bypass renamed as DND-KMP Expressway on Google Maps". Hindustan. 23 July 2023.
  2. ^ "59-km six-lane road to connect DND, Ring Road with Delhi-Mumbai expressway - delhi news". Hindustan Times. Retrieved 4 August 2020.
  3. ^ "Delhi-Mumbai Expressway will be linked to Jewar Airport". Times of India. 8 July 2022.
  4. ^ "Jewar Airport और Delhi-Mumbai एक्‍सप्रेसवे से लिंक रहेगा DND-Faridabad-KMP Expressway, रूट मैप देखिए". Navbharat Times. 25 March 2023.
  5. ^ "DND-Faridabad-KMP Expressway to be connected with Delhi-Mumbai Expressway, Jewar Airport, check routes". DNA India. 27 March 2023.
  6. ^ "दिल्ली-मुंबई एक्सप्रेस-वे पर हरियाणा के फरीदाबाद से आ रही खुशखबरी, जानें फायदा". Dainik Jagran. 8 April 2022.
  7. ^ "Work awarded for new Delhi-Mumbai e-way link". Times of India.
  8. ^ "Delhi NCR: Six-lane highway to connect ring road-DND junction with Delhi-Mumbai Expressway". Times Now. Retrieved 4 August 2020.
  9. ^ a b "Contract award status of Delhi–Mumbai Expressway as of May 2021" (PDF). NHAI. 28 May 2021.
  10. ^ "Jewar International Airport will be linked to Delhi-Mumbai Expressway". News18. 16 September 2021.
  11. ^ "Nitin Gadkari to lay foundation stone for Rs 3,580 crore project to decongest Delhi". Economic Times.
  12. ^ "NHAI invites bids for highways under Bharatmala Pariyojana". Construction Week Online. 22 December 2019.
  13. ^ "Soil testing for Delhi-Mumbai Expressway link begins in Faridabad". Times of India.
  14. ^ "NHAI to start work on crucial decongestion projects in Delhi this year". Hindustan Times. 10 February 2021.
  15. ^ "NHAI to raze 500 structures for Delhi-Mumbai Expressway". The Tribune. 9 October 2021.
  16. ^ "दिल्ली-मुम्बई एक्सप्रेसवे के पहले चरण का निर्माण शुरू, नोएडा से बनकर जा रहा प्री-कास्ट मैटेरियल". TriCity Today. 22 March 2022.
  17. ^ "Tender opens for Expressway to link Faridabad & Jewar Airport". The Tribune. 31 July 2022.
  18. ^ "Noida Airport: 2 साल में दिल्ली-मुंबई एक्सप्रेसवे से जुड़ेगा जेवर एयरपोर्ट, 6 लेन पर खर्च होंगे 16.60 अरब, NHAI ने निकाला टेंडर". Navbharat Times. 31 July 2022.
  19. ^ "Ballabhgarh: Delhi-MumbaiExpressway link opens this week". The Times of India. 20 February 2023.
  20. ^ "Entire stretch from DND Flyway to Delhi-Mumbai Expressway to be opened by year end: Nitin Gadkari". The Times of India. 15 February 2024.