Nuclear power in the Czech Republic

Source: Wikipedia, the free encyclopedia.

Nuclear power stations in the Czech Republic (view)
 Active plants
 Planned plants

The Czech Republic operates two nuclear power plants: Temelín and Dukovany. As of 2019 the government intends to increase the share of nuclear electricity production from 30 % to 58 %. To this end, a new reactor is to be constructed at the Dukovany site, which will replace older units by 2035. New capacities are also expected to be added at the Temelín site.[1]

Map of nuclear power plants and research reactors

History

Temelín NPP

In 1956 a decision was made to build the first nuclear power station in

accident stopped energy production and since 1979 the reactor has been partly dismantled, but not decommissioned.[citation needed
]

In 1970 an agreement with the Soviet Union was made to build two power stations of the VVER reactor design. One plant was built again in Jaslovské Bohunice, the other in Dukovany (southern Moravia), both equipped with four reactors VVER-440 v. 213 producing 440 MWe each. The first new reactor in Jaslovské Bohunice was activated in 1978, the remaining 7 during the 1980s.[citation needed]

At the end of the 1970s a decision was made to build two more power stations: Temelín (southern Bohemia, 4 × VVER-1000, 1000 MWe) and

Mochovce (southern Slovakia, 4 × VVER-440 v. 213, 440 MWe). In 1990, due to a decision by the government of Petr Pithart,[citation needed] the Temelín station was limited to two reactors. The construction of Temelín also experienced delays and went over budget.[citation needed
]

The

used nuclear fuel was developed at the Řež nuclear research institute at Řež.[2][3][4]

Spent fuel

The Czech Republic has no state policy on storage or reprocessing of

spent fuel until the Radioactive Waste Repository Authority (RAWRA) assumes responsibility for it. The RAWRA will select a permanent location for storage by 2015 and construction will begin on this site after 2050.[5]

Czech—Austrian relations

The Czech Republic and Austria have had disagreements concerning the Temelín Nuclear Power Station only 50 km from the Czech–Austrian border. Austria had threatened the Czech Republic with difficulties in joining the EU if the plant was commissioned. Other opponents to this power plant claimed that it had the same design as the Chernobyl.[citation needed] In fact, Chernobyl had RBMKs, and Temelín would have VVERs.[citation needed] The Czech President at the time, Václav Havel, called the plant "megalomaniacal".[6]

Proposed expansion

The Czech Energy Policy of 2004 envisaged building two or more large reactors to replace Dukovany power plant after 2020. The plans announced in 2006 envisaged construction of one 1,500 MWe unit at Temelín after 2020, and a second to follow.[7]

In 2019 the Czech government gave preliminary approval for at least one new nuclear power unit at Dukovany Nuclear Power Station for about 2035 to replace four units expected to shut down between 2035 and 2037. The financial model proposed is a state guarantee so finance can be obtained at government interest rates, but no subsidy on operating costs or above market-price electricity rates.[1]

Blahutovice

Blahutovice, a village located in an isolated and thinly populated area, was selected in 1986 because of convenient geological conditions. A power station (JEBL) with two VVER-1000 reactors was proposed, together with a new dam in Hustopeče nad Bečvou. In 2000, the proposed start date for construction was not expected until 2015, if at all.

Tetov

Initially, Opatovice nad Labem (home of a large coal powered power plant) was selected, but its location between the cities of Hradec Králové and Pardubice was unfavorable and the more distant village of Tetov was chosen. One plan suggested building a nuclear heating plant in Opatovice nad Labem instead.

The power station required an area of 150 hectares and was to have two or four VVER-1000 reactors, producing 1000 MWe each and also providing heating for the Hradec Králové-Pardubice agglomeration, and for Prague (using a 67 km long steam pipeline). Construction was to begin in 1996 and the reactors to be activated between 2004–2008. The cost was estimated to be 60 billion (109) Kčs.[11]

Nuclear waste storage

Nuclear waste produced by the power stations and the other smaller reactors in the country is exported to Russia (or the Soviet Union before 1991), who supply the enriched uranium. A programme from 1980s recommended the building of an underground storage site to keep waste for reprocessing in the future. Geological exploration started during the second half of the 1990s. Eleven candidate locations have been selected but the process is not finished as of 2006. The possibility of storing waste on the Temelín station site is being considered.

Public opinion

Most Czechs support further expansion of nuclear power use, with support at 60 % in 2007.[12]

Those living near nuclear waste storage facilities argue that proposals for expansion of nuclear power block development of such areas, discourage investment and make the areas unattractive for tourists.[citation needed] Several villages organized referendums against planned waste storage and regional governments have tried to put up legal and administrative obstacles to new stations.[citation needed]

In 2008, a poll found that 64 % of Czechs agree with the use of nuclear power, the highest level of support of the 27 EU countries surveyed, alongside Lithuania. Furthermore, the poll indicated that support was rising, from 52 % in 2004 to 64 % in 2008.[13]

An IBRS survey found that support for nuclear energy has risen to 65 % in 2021.[14]

See also

References

  1. ^ a b "Czech state to back new nuclear units". World Nuclear News. 9 July 2019. Retrieved 10 July 2019.
  2. ^ AN EXPERIENCE ON DRY NUCLEAR FUEL REPROCESSING IN THE CZECH REPUBLIC
  3. ^ R&D OF PYROCHEMICAL PARTITIONING IN THE CZECH REPUBLIC
  4. ^ DEVELOPMENT OF URANIUM OXIDE POWDER DOSING FOR FLUORIDE VOLATILITY SEPARATION PROCESS Archived 2004-11-17 at the Wayback Machine
  5. ^ "Nuclear Power in the Czech Republic". World Nuclear Association. February 2007.
  6. ^ "Czech reactor: Twenty years of controversy". BBC News. 2000-08-13.
  7. ^ "Nuclear Power in Czech Republic". World Nuclear Association. February 2007. Retrieved 2007-07-15.
  8. ^ "Plans to expand Temelín" (in Czech). June 2005. Retrieved 2007-03-31.
  9. World Nuclear News
    . 3 August 2009. Retrieved 2009-08-03.
  10. ČEZ
    . December 2005. pp. 56–59. Retrieved 2007-03-30.
  11. MF Dnes
    . June 2006. Retrieved 2007-03-31.
  12. ^ "People agree to finish Temelín" (in Czech). March 2007. Retrieved 2007-03-31.
  13. ^ http://www.cez.cz/cs/vyroba-elektriny/zvazovana-dostavba-elektrarny-temelin/postoj-ceske-verejnosti-k-jaderne-energetice.html[dead link]
  14. ^ "Czech support for nuclear rises in energy crisis". World Nuclear News. 2021-12-23.

External links