History of the Long Island Rail Road
The
Gateway to Boston, 1832–1840s
The LIRR's history stretches back to the
Since its plan was not to serve local traffic on Long Island, the LIRR chose not to serve existing communities along the shores of the island, but built straight down the middle of the island, which was largely uninhabited at the time and relatively free of
After one or more trial runs in February 1836, the Brooklyn and Jamaica opened its full line, roughly along the present
Hicksville remained the terminal for the next four years due to the
On May 16, 1836 supplement to the charter authorized a branch to
Later in 1842, the line reached
The LIRR bought the
The LIRR began operating the Worcester and New Haven steamboats in 1845, and established a second route to Boston via steamboat to
Local focus, 1840s–1875
The final blow came in December 1848, when the
Branches to the north and south shores
In 1851, under the General Railroad Act, the
However, it was not yet complete. The line was intended to go to through White Oak Tree, present-day Laurel Hill before going to Cold Spring Harbor. There was not money for the project, and the LIRR got an extension from the Legislature in February 1858. Because of the Civil War the extension was impractical. The Hicksville and Cold Spring Branch Railroad had legislative approval to run as far as Cold Spring Harbor, but Charlick wanted an extension to Huntington. As a result, permission for the three miles of right-of-way had to be obtained. The iron to extend the railroad had been purchased in February 1866. The right-of-way began to be graded in May 1867. The right-of way and track that was once intended to terminate at Cold Spring Harbor was abandoned and a new right-of-way running east was built.[25]
The line was extended to Huntington on January 13, 1868 and to Northport on April 25, 1868.
When the LIRR was charted in 1834, it was authorized to construct a branch line to Sag Harbor, and in 1854, a survey was made for a branch from Riverhead to the Hamptons and Sag Harbor. However, the line was not built.
The Glen Cove Branch Railroad was incorporated on December 3, 1858. The Locust Valley Branch, now the Oyster Bay Branch, opened from Mineola on the main line north to Glen Head on January 23, 1865,[33] and to Glen Cove in 1867,[34] before finally being extended to Locust Valley on April 19, 1869.[30][35]
However, the building of branches was retarded by the LIRR presidency of Oliver Charlick between 1863 and 1875. Charlick was known for only building branches where necessary to cut off plans by locals to build competing lines.[36]
Charlick also rebuilt the wharf at Greenport in 1870, and operated a new Boston route via
Brooklyn
The city of Brooklyn banned the LIRR from using
Despite opposition from the
The LIRR chartered the New York and Jamaica Railroad on September 3, 1859,
The new line to Hunters Point was officially opened on May 9, 1861, with regular service starting May 10. A ferry connection (
Competition and consolidation on Long Island, 1854–1880
From the 1850s through the 1870s rail service expanded considerably throughout Long Island, with several competitors vying for market share and making small, if any, profits. In 1875–76 a wealthy
The first non-LIRR line on Long Island was the
In 1857, it fell into the hands of a receiver, and it was sold under foreclosure the following year. The company was reorganized in 1859 as the New York and Flushing Railroad when Oliver Charlick took over the railroad,
The line was intended to use the LIRR tracks from Hunter's Point to Woodside, where it would branch off and then run parallel to Jackson Avenue to Flushing, providing a more direct route than the New York and Flushing Railroad's. Work on the project begun in 1864, however, not much progress was made over the next three years because of legal problems in securing the right-of-way.
The LIRR benefitted by preventing the
A group of College Point and Whitestone citizens, feeling they had been tricked by the LIRR, convinced wealthy residents of
This new line attracted most of the traffic from the older New York and Flushing, and the LIRR wanted to get rid of its Flushing branch. In 1869, the state legislature authorized the Flushing and North Side to buy the New York and Flushing east of the LIRR crossing at
Soon after it sold the New York and Flushing to the Flushing and North Side, the LIRR decided to enter the Flushing business again, and chartered the Newtown and Flushing Railroad ("White Line") on March 8, 1871.[61] It opened on November 10, 1873, paralleling the Flushing and North Side to the south and beginning a rate war.[28]
The first major competitor to the LIRR, the
In order to obtain a terminal along the East River, the SSRLI asked the LIRR if a track connection could be made in Jamaica so that the LIRR's line could be used to Hunters Point. However, the LIRR refused and it stopped attempts by the South Side to use the Brooklyn, Central and Jamaica Railroad and to purchase the New York and Flushing Railroad, which would have connected at Laurel Hill. Finally,
In 1872 the South Side opened a new alignment, the
Charlick decided to build his own line to
In 1904 – 1905, the line was going to be connected to the Atlantic Division, and property was purchased for the connection in March 1905, and it was completed and electrified in 1908. Service was never started and the line was unused until 1918, when the tracks were removed for other uses because of World War I. The line was rebuilt once again and was electrified once there was a building boom in the area in 1934. However, because of the Great Depression, the line was not used and it was torn up before being sold in 1934.[68]
The Central Railroad of Long Island was incorporated in 1871 by
The South Side entered
President
Amidst complaints over the way the consolidation was handled,
In late March 1877, Brooklyn finally authorized the LIRR to return to Atlantic Avenue with steam locomotives, and the LIRR leased the main line of the
On August 7, 1876, the
Austin Corbin years, 1880–1900
Hoping to build a line from Bay Ridge through East New York to Valley Stream, in 1870, the New York and Hempstead Railroad was incorporated. The line was leased by the South Side Railroad after two years of grading and excavating, but because of the financial panic of 1873 the project was drawn to a halt. This concept was resurrected when the New York, Bay Ridge and Jamaica Railroad was created in 1875, with its line following the current path of the Bay Ridge Branch freight branch of the LIRR. The line was finished up to
Having been sold to
In order to continue the line into northern Brooklyn, the
In 1878, Austin Corbin organized the
Corbin was however able to acquire control of the LIRR in 1880,[2] and brought it out of bankruptcy, becoming its president in 1881. Once Corbin had control of the LIRR, it was decided to standard gauge the Manhattan Beach Line and connect it with both the LIRR's Atlantic Branch and Lower Montauk Branch. This was completed in 1883, and this meant that Greenpoint segment was no longer necessary, and the portion west of South Side Crossing to Greenpoint was abandoned and torn up around 1890. The LIRR leased the NY&MB in 1882, not merging it until 1925. Under Corbin's entire 16-year control, the LIRR continuously paid dividends to its stockholders.[84]
A number of new extensions and branches were built under his ownership.
In June 1879, under a mortgage foreclosure, what was left of the South Side Railroad was sold, and it was conveyed to the newly organized
The
Corbin attempted to buy the
In 1890, the Main Line was double tracked to
The LIRR tried a Boston route again in 1891, this time from
But the most notable line built by Frank Sherman Benson was the Montauk Extension Railroad from Amagansett, NY east to Fort Pond Bay in Montauk. Austin Corbin purchased land in Montauk with a plan was to build a deep water port at Fort Pond Bay, where trans-Atlantic passengers could disembark and travel into New York at "a mile a minute" (100 km/h) and thus save a day in travel time. Arthur W. Benson, president of Brooklyn Gas and Light Company and founder of Bensonhurst, Brooklyn, had acquired 10,000 acres (40 km2) of land at auction by court order pursuant to an action in partition in 1879 for $151. In 1882 Benson purchased 1,100 acres of land at Napeague sold Corbin's real estate company right-of-way through Montauk to Fort Pond Bay. By 1895 Corbin had acquired a further 4,000 acres (16 km2) from the Estate of Arthur W. Benson. The plans for Montauk Extension Railroad from Amagansett to Fort Pond Bay were signed by Frank Sherman Benson and are on file at the County Center in Riverhead. It was incorporated May 25, 1893 and opened in 1895.[2][74][98]
In 1885, a connection was made between the
An incline connecting the Brooklyn Elevated's
With the death of Austin Corbin in June 1896 the LIRR was reorganized and the decline of the Manhattan Beach line started.
In 1898, an extension of the current
On May 13, 1899, the LIRR bought the
Pennsylvania Railroad ownership, 1900–1949
Year | Traffic |
---|---|
1925 | 1573 |
1929 | 1893 |
1933 | 1304 |
1944 | 2055 |
1960 | 1477 |
1970 | 1761 |
Corbin began planning for direct access to
The James Slip and Annex ferries to Lower Manhattan were abandoned in 1907 and 1908, before the tunnel was completed, but the ferry to 34th Street continued to operate until 1925.[112]
The new station and tunnel network provided direct rail service from Long Island to Manhattan, resulting in vast increases in both total passengers and daily commuters. Total annual ridership increased from 34 million in 1911, the first full year that Penn Station was in operation, to a peak of 119 million in 1929. By then, 61.7% of LIRR passengers were daily commuters, up from over 30% in 1911. But the
During this period, the LIRR gained control of most of the connecting and competing trolley lines on Long Island. Its first acquisitions were the Ocean Electric Railway and Huntington Railroad, both by 1899.[117] Several more lines were built in the early 1900s, and Long Island Consolidated Electrical Companies was incorporated in 1905 as a holding company for the LIRR's trolley properties.[118] It gained 50% ownership in the closely related New York and Long Island Traction Company and Long Island Electric Railway in 1905 and 1906 respectively, the other half going to the Interborough Rapid Transit Company.[119][120] Most of the lines had ceased operating by 1924, and the NY&LI and LIE were both sold at foreclosure in 1926. The final abandonment was the Ocean Electric on Rockaway Beach Boulevard in 1928.[112][121]In 1905, the
Year | Traffic |
---|---|
1925 | 163 |
1933 | 97 |
1944 | 148 |
1960 | 77 |
1970 | 73 |
When Belmont Park opened on May 4, 1905, about 19,000 passengers—nearly half of all attendees—took the railroad to the racetrack on opening day.[122][123] The first electric trains to Belmont Park ran on October 2, 1905, the opening day of the fall meet.[124] The original station was located south of Hempstead Turnpike; the present terminal north of Hempstead Turnpike was opened in 1957.[125][126]
The LIRR also began
its urban and suburban lines in the 1900s.Because of increasing fatalities at the Atlantic Branch's 50 grade crossings, a law was passed from the City of Brooklyn and the City of New York to remove grade crossings in 1897. As part of the law, a tunnel would have been built to Lower Manhattan, but because of the large cost, it was removed in 1900. Work commenced in December 1901, after a new version of the law was passed on April 8, 1901 without any mention to the tunnel. The portion from Flatbush Avenue to Bedford Avenue the line was to be a tunnel, and the portion from Nostrand Avenue to Ralph Avenue was to be elevated. The next section, between Ralph Avenue and Howard Avenue was to be built as a tunnel, and the remaining portion to Atkins Avenue would have been an elevated structure. The first portion of the line to be opened was between Manhattan Crossing and Atkins Avenue. This portion opened on May 28, 1903, and the second part, the elevated from Nostrand Avenue to Ralph Avenue, opened on November 23. to Manhattan Crossing, The first tunnel segment, the one between Ralph Avenue and Howard Avenue, opened in 1904. Because of delays resulting in the construction of the new Flatbush Avenue terminal, service to the new underground Flatbush Avenue did not commence until November 5, 1905. Prior to the opening of the underground station, trains used a connection with the Brooklyn Rapid Transit's Fifth Avenue Elevated and temporary wooden platforms were built on the connection. The new terminal opened on April 1, 1907. The easternmost elevated section of the line was replaced by a tunnel around the year 1940.[127]
The first electrification was on the
A big grade-elimination project was started on the Bay Ridge Branch in 1906 and was completed by 1915.[82] Later electrification included the Montauk Division from Jamaica out to Babylon in 1925[128] and the Bay Ridge Branch (for New York, New Haven and Hartford Railroad freight off the 1916 Hell Gate Bridge) in 1927.[129] The PRR began directly operating the LIRR under lease on October 1, 1928.[130]
The railroad continued to actively promote Long Island as an attractive residential area. The railroad's Passenger Department, led by Hal B. Fullerton, issued numerous publications touting the virtues of life on Long Island as compared with city life. As explained by historian Charles Sachs, Fullerton spent thirty years in the Passenger Department "promoting and advertising events, activities, or plans that would bring public attention to the island's potential for sport, recreation, business, and residential development for both the middle classes and urban elite."[131]
The price of a monthly commute ticket was unchanged from 1918 to 1947: $10.56 Penn Station to Mineola, $13.81 to Babylon, $10.07 to stations from The Raunt to Rockaway Park. Monthlies to Brooklyn were $2.20 less.[citation needed]
At the end of 1925 the LIRR operated on 397 miles of road and 957 miles of track; mileages in 1970 were 326 and 738.[citation needed]
Palsgraf v. LIRR (1928) is a major case in American Tort law which established the legal standard of "proximate cause" based on foreseeability. The case involved a passenger (Palsgraf) who was injured on the platform as the result of a chain of events (another passenger dropping a package on the tracks which turned out to be fireworks that exploded and indirectly caused the injury to Mrs. Palsgraf) which the court deemed unforeseeable on the part of the LIRR. It is a milestone decision in American law.[citation needed]
On October 19, 1926, the portion of the line between Valley Stream and Franklin Avenue in Garden City was electrified and it was inaugurated with a special train.
In the 1930s, the use of the Manorville Branch for service between the forks declined, and limited service using the line continued into the World War II years, and in 1946 the line was removed from timetables, and it was no longer used after March 3, 1949. On November 25, 1949, the Interstate Commerce Commission approved the LIRR's request to abandon the line, and the tracks were removed in the winter of 1950.[32]
Lean years, 1949–1966
Rail service – and in particular passenger rail service – declined dramatically after World War II as it faced competition from the rise of the automobile and improved air travel. Passenger rail travel was very vulnerable because government regulations required certain levels of service even if unprofitable.
Greater New York, unlike most other cities, fared much better due to the fact that day-to-day life was built upon the commuter culture mentality. Both its subway and commuter rail systems continued to be heavily used despite years of neglect. As Long Island's population increased dramatically after World War II it became readily apparent that the public parkway and highway system would prove to be totally inadequate for the population. The LIRR was looked to as the solution to the problem, however, the railroad was in a sad state of neglect.[citation needed]
Despite a doubling of operating costs since 1917, the LIRR was not permitted to raise its fares.[136] It declared bankruptcy on March 2, 1949, after which the PRR stopped supporting its debts, transferring it to the subsidiary American Contract and Trust Company.[137] Direct PRR operations ended on May 1.[138] In the next year, the LIRR suffered three accidents (the Rockville Centre, Huntington and Kew Gardens train crashes), killing a total of 115 passengers. The Jamaica Bay trestle on the Rockaway Beach Branch caught fire in May 1950, and it was abandoned on October 3, 1955 south of Ozone Park.[139] It was then sold to New York City, which rebuilt it for the IND Rockaway Line subway extension.[140]
The LIRR rolling stock, most of which dated from the early 1900s, proved to be a major problem. Built at a time when the average person's height and weight was smaller, the seating arrangements in the cars proved to be completely inadequate for mid-century commuters, who were much bigger in stature. The antiquated stock was also noted for frequently breaking down. It was not uncommon in an average day for there to be nearly ten to fifteen cancelled trains. Noted New York writer
The LIRR also took other steps to improve its physical image and its operations. In the 1950s they started a new publicity campaign, adopting a new "Dashing Dan" and "Dashing Dottie" logo and painted its trains in a gray color scheme.
In the summer of 1951, as a cost-cutting measure, all trains operating in and out of Penn Station using electric locomotives were changed to originate and terminate in Jamaica or Long Island City. As a result, there was no direct service to New York, and passengers were forced to switch to an electric train, and "the moniker "change at Jamaica" became the norm".[143]
In August 1954, the state of New York passed legislation that took the LIRR out of bankruptcy and designated it as a Railroad Redevelopment Corporation, and over twelve years, $60 million was provided to improve the LIRR. This improvement focused on the western electric territory. This was complemented by tax abatements for the LIRR and the PRR. It was then promised by the PRR that it would reinvest profits into the LIRR's improvement program. At this time, 220 new Pullman Standard coaches were ordered in order to replace older cars from before World War I, which were then scrapped. About 700 of the older cars were rebuilt with improved heating and ventilation, new floors, new seating, and new lighting. Many grade crossings were eliminated and heavily travelled lines were refurbished.[3]
In 1956, some freight trains were moved by the LIRR to overnight hours, allowing for better running times and cutting service times to Eastern Suffolk County.[143]
By 1963, the
Road n' Rail bus service
For some time, the LIRR had tried to attract customers on the
An additional reason was competition.
The new plan replaced trains with six daily bus round trips between
The original Road n' Rail buses were operated under contract with the LIRR, by
In the beginning of Summer 1973, the LIRR discontinued direct Huntington to Riverhead bus service, relying on a faster route.
1963: the Better Rail Service for Nassau County Plan
In June 1963, the Nassau County Planning Commission issued a report and the Nassau County Department of Transportation and Franchises issued a report called "Better Rail Service for Nassau County". Many projects were proposed in the report. As part of the project, the
Jamaica station would have been reconstructed, with direct access to the New York City Subway and a provision for express bus service to JFK Airport. Woodside would have been rehabilitated with provisions for the proposed Queens Bypass subway line that would have run alongside the Main Line before either using the abandoned Rockaway Beach Branch or merging with the IND Queens Boulevard Line at Forest Hills. A provision for express bus service running to LaGuardia Airport via the Brooklyn Queens Expressway would have been made. Service to Grand Central would have been provided with a one track loop, branching off in Sunnyside with a tunnel to 50th Street and Park Avenue. Three stations would have been built; one at 52nd Street between Lexington Avenue and Third Avenue, one under Grand Central Terminal between 45th Street and 47th Street, and a station on Madison Avenue between 35th Street and 37th Street. The line would connect with East River Tunnels at 33rd and 32nd Streets so that trains could continue to Long Island. A provision would have been built for a possible future extension down Madison Avenue. Also, as part of the plan, the Atlantic Branch would have been turned over to the New York City Subway to allow for a lower fare for people commuting to Lower Manhattan, and it would have provided a high speed subway service. This subway service, under the plan, would have ultimately been extended to Belmont Park eliminating the need for LIRR trains to serve local stations between Jamaica and Belmont Park. The whole project would have cost $103 million, taking six years to complete.[150]
State ownership, 1966–present
1960s–1980s: M1s, push-pulls, and electrification extensions
The PRR was looking to rid itself of the money-losing LIRR, its most costly subsidiary,
Once under State ownership, the Dashing Dan logo was dropped and a new paint scheme was created for locomotives and coaches. The new electric coaches, the M1 cars, replaced the aging Multiple Unit fleet. The cars were put into service between 1968 and 1972.[3] The cars were called "Metropolitans", and they were clad in stainless steel, with air-conditioning and lighting, as well as semi-bucket seating. Quarter point doors were installed in order to speed loading and unloading from high-level platforms. High-level platforms were required by the design of the M1 and LIRR carpenters engaged in a speeded up program to build temporary high-level platforms at all stations within electrified territory. All electrified branches became completely equipped with high-level platforms when the final branch, the West Hempstead Branch, was completed in 1973. A total of 53 new high-level platforms were constructed at 38 stations in electric territory that originally had low platforms.[3] Ultimately, they were replaced by permanent concrete platforms at a slower pace.[152]
By the mid-1970s the M1s comprised the entire electric fleet, supplemented by 174 new M3 cars between 1985 and 1986. The newer, postwar single-level electric MU cars were converted to operate behind diesels, joining the postwar diesel-hauled coaches already in that service whose HVAC systems were converted from
Two more
In 1980, a monthly to Huntington from Penn cost $80, but by 1981, it had risen to $102.75 (equivalent to $344 in 2023).[158] The Long Island Rail Road celebrated its 150th anniversary in 1984.[159]
In June 1987, a new storage yard, the
In February 1988, the LIRR forbade smoking on its trains, as well as in all enclosed station areas.[3] During this time frame, wooden track ties on the Main Line, as well as other major lines, were replaced with new concrete ties. Major upgrades to signals and interlockings were done as part of bigger projects that provided electrification extensions or new main line tracks.[3]
Major grade crossing elimination carried on through the 1970s, until the goal of a crossing-free Babylon Branch was finally achieved at
1990s–2000s: Penn Station, bilevels and dual-modes, and M7s
Under Governor
On December 7, 1993, six people were killed and 19 others injured in a mass shooting on a train near Merillon Avenue station.[167]
A 25-year decline in freight on Long Island led to the MTA franchising the LIRR's
More capital improvement projects took place during the late 1990s. In 1998, the railroad began to replace its aging diesel and parlor car fleet, which dated from the 1940s and 1950s, by purchasing new bi-level coaches. In doing so the railroad also began to install completely
The railroad also purchased new DE (Diesel Electric) 30 and DE-DM (Diesel Electric and Dual Mode) 30 diesel engines capable of providing push-pull service with the bilevels. In October 2002, a total of 836 Bombardier-built M7 cars began to replace the entire M1 fleet. By the end of 2006, the M7s completely replaced the aging M1 fleet. The M7s were able to deal better with snowstorms than their predecessors.[3]
The MTA had announced in October 2002 that it had planned to merge the LIRR and the
In 2006, an 18-year-old woman died at the Woodside station after falling into the gap between the platform and train, and subsequently getting hit by an oncoming passenger train.[176][177] The death resulted in the LIRR and Metro-North Railroad implementing an aggressive platform gap mitigation[176]: 7 platform conductor personnel, and "Watch the gap" programs.[178][179][176]: 6
On June 4, 2007, MTA announced the appointment of Helena Williams to the position of President of the LIRR. Williams succeeded Raymond P. Kenny, the interim President who had held the office since James J. Dermody stepped down in September 2006.[180] Williams's promotion marks the first time this position has been held by a woman.[181]
The Long Island Rail Road celebrated its 175th anniversary on April 22, 2009 with a trip on the TC82 inspection car from Brooklyn to Greenport, the original LIRR main line. The train stopped along the way to pick up proclamations from county executives in Nassau and Suffolk counties.[182]
2010s: Expansions and Hurricane Sandy
In 2007, the LIRR began work on
As part of East Side Access, five "readiness projects" are also under construction to increase peak-hour capacity across the LIRR system in preparation for expanded peak-hour service after the completion of East Side Access. Together, they are expected to cost $495 million.[189][190] The projects include adding a new platform at Jamaica station for trains to and from Atlantic Terminal;[191] adding storage tracks near Massapequa station[190] and Great Neck station;[192] and expanding the Port Washington Yard near Port Washington station[190] and the Ronkonkoma Yard adjacent to Ronkonkoma station.[193][190]
In 2012, the LIRR started work on constructing a second track along the Ronkonkoma Branch between Farmingdale and Ronkonkoma stations. Before the start of the project, the largely single-track Ronkonkoma Branch limited train capacity to one train per hour in each direction.[194] The entire project cost $387.2 million and was completed in September 2018.[195][196]
The LIRR was severely affected by Hurricane Sandy in 2012. In anticipation of the storm, the LIRR was shut down on October 29, 2012, and the railroad moved trains out of low-lying areas such as the West Side Yard. As a result of the storm's record breaking storm surge, many parts of the system were inundated with water, including the East River Tunnels, the West Side Yard, and the Long Beach Branch.[197] It took the railroad seven weeks to restore full rush hour service.[198] In the late 2010s, the LIRR began work on projects to replace components on the Long Beach Branch and West Side Yard that had been damaged during Hurricane Sandy. However, as of October 2018[update], the Long Beach Branch and West Side Yard projects had not been completed, and the replacement of the East River Tunnels has not started.[199]
On January 4, 2017, a train derailed at Atlantic Terminal, injuring 103 passengers.[200][201] On March 23, 2018, a Ronkonkoma Branch train heading towards Penn Station struck a car that drove the tracks from a GPS at Mineola station, no injuries are reported.[202] On February 26, 2019, a Ronkonkoma Branch train headed for Penn Station struck a truck and derailed, damaging the platform at the Westbury station and killing all three occupants of the truck.[203]
To accommodate an expected increase in Long Island Rail Road ridership once the East Side Access is completed, the LIRR planned to build a third Main Line track from
In July 2019, plans to open a
On January 23, 2023, Grand Central Madison was officially opened as work on East Side Access concluded after 15 years. Limited shuttle service to Jamaica began on January 25, 2023, with full through service east of Jamaica starting in late February of that same year.
See also
- List of former Long Island Rail Road lines
- Long Island Rail Road fleet
- List of presidents and trustees of the Long Island Rail Road
- 1993 Long Island Rail Road shooting
- Montauk land claim
Notes
- ^ "About the MTA Long Island Rail Road". Metropolitan Transportation Authority. 2016. Archived from the original on March 12, 2007. Retrieved July 15, 2016.
- ^ a b c d e f g h "LIRR Early History". lirrhistory.com. Archived from the original on March 4, 2000. Retrieved May 1, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ a b c d e f g h i j k l Fischler (2007).
- ^ a b c "BROOKLYN & JAMAICA RAIL ROAD, ATLANTIC AVENUE". www.arrts-arrchives.com. Retrieved May 1, 2016.
- ^ a b c d e f g h i j k l m n o Smith (1958).
- ^ Ziel & Foster (1987), p. 8.
- ^ An Act to Incorporate the Long-Island Rail-Road Company, Passed April 24, 1834, reproduced at Early History of the LIRR[usurped]
- ^ Ziel & Foster (1987).
- ^ Smith (1958), p. 8.
- ^ PRR Chronology, 1835 (2015).
- ^ a b c "PRR Chronology, 1836" (PDF)., June 2004 Edition
- ^ Ziel & Foster (1987), pp. 8 and 9.
- ^ PRR Chronology, 1837 (2015).
- ^ "UNION COURSE RACE TRACK". www.arrts-arrchives.com. Retrieved May 1, 2016.
- ^ "PRR Chronology, 1839" (PDF)., June 2004 Edition
- ^ "PRR Chronology, 1844" (PDF)., May 2004 Edition
- ^ Ziel & Foster (1987), pp. 10, 80.
- ^ "PRR Chronology, 1848" (PDF)., April 2005 Edition
- ^ "PRR Chronology, 1850" (PDF)., March 2005 Edition
- ^ Ziel & Foster (1987), p. 11.
- ^ "PRR Chronology, 1851" (PDF)., March 2005 Edition
- ^ "PRR Chronology, 1842" (PDF)., May 2004 Edition
- ^ Ziel & Foster (1987), p. 12.
- ^ PRR Chronology, 1862 (2015).
- ^ a b "H&CSBrRR". arrts-arrchives.com. Retrieved May 26, 2016.
- ^ a b "PRR Chronology, 1854" (PDF)., March 2005 Edition
- ^ a b "PRR Chronology, 1868" (PDF)., June 2004 Edition
- ^ a b c d "PRR Chronology, 1873" (PDF)., February 2005 Edition
- ^ "OLD NORTHPORT". arrts-arrchives.com. Retrieved May 26, 2016.
- ^ a b c d e f "PRR Chronology, 1869" (PDF)., June 2004 Edition
- ^ a b PRR Chronology, 1870 (2015).
- ^ a b c d e "Change at Manorville or Eastport: The History of the Long Island Rail Road's Manorville-Eastport Spur". Derek Stadler. January 10, 2015. Retrieved May 29, 2016.
- ^ PRR Chronology, 1865 (2015).
- ^ a b c PRR Chronology, 1867 (2015).
- ^ a b c "Benefitting the Gold Coast: A History of the Long Island Rail Road's Preeminent Service to Locust Valley". Derek Stadler. October 5, 2014. Retrieved May 26, 2016.
- ^ Ziel & Foster (1987), pp. 13–14.
- ^ Ziel & Foster (1987), pp. 80, 82.
- ^ a b c d e "PRR Chronology, 1872" (PDF)., February 2005 Edition
- ^ Brooklyn Daily Eagle. Brooklyn, NY. July 5, 1851. p. 4.
{{cite news}}
: Missing or empty|title=
(help) - ^ "Steam on Atlantic Street". Brooklyn Daily Eagle. Brooklyn, NY. July 11, 1851. p. 3.
- ^ "The Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. October 2, 1851. p. 2.
- ^ "New Stage Arrangements". Brooklyn Daily Eagle. Brooklyn, NY. October 8, 1851. p. 3.
- ^ "The Railroad Company, and the Corporation, and Common Council". Brooklyn Daily Eagle. Brooklyn, NY. October 10, 1851. p. 2.
- ^ Brooklyn Daily Eagle. Brooklyn, NY. January 27, 1859. p. 2.
{{cite news}}
: Missing or empty|title=
(help) - ^ Brooklyn Daily Eagle. Brooklyn, NY. June 2, 1859. p. 1.
{{cite news}}
: Missing or empty|title=
(help) - ^ a b "PRR Chronology, 1859" (PDF)., March 2005 Edition
- ^ a b "PRR Chronology, 1860" (PDF)., May 2004 Edition
- ^ "The Brooklyn Central Railroad". Brooklyn Daily Eagle. Brooklyn, NY. August 29, 1860. p. 3.
- ^ "The Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. May 10, 1861. p. 2.
- ^ "Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. May 18, 1861. p. 2.
- ^ "Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. October 8, 1861. p. 1.
- ^ "Long Island Railroad – Change of Terminus". Brooklyn Daily Eagle. Brooklyn, NY. October 10, 1861. p. 3.
- ^ "Travel". Brooklyn Daily Eagle. Brooklyn, NY. June 8, 1861. p. 3.
- New York Times, South Ferry Atlantic-Street Railroad, December 23, 1861, page 8
- ^ a b c d e "Flushing". www.lirrhistory.com. Archived from the original on March 3, 2000. Retrieved May 8, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ "Reports of the Committee and Engineer on the Preliminary Survey of the North Side Railroad". lirrhistory.com. 1854. Archived from the original on June 22, 2002. Retrieved May 8, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ PRR Chronology, 1864 (2015).
- ^ a b PRR Chronology, 1866 (2015).
- ^ a b c Ziel & Foster (1987), p. 36.
- ^ a b c d e f Ross, Peter (1903). "A History of Long Island From its Earliest Settlement to the Present Time, History of the Long Island Railroad". The Dunton Archive. Retrieved May 18, 2016. This article incorporates text from this source, which is in the public domain.
- ^ a b c d "PRR Chronology, 1871" (PDF). Archived from the original (PDF) on October 14, 2013. Retrieved February 8, 2007., January 2005 Edition
- ^ "LIRR History Part 1 - Page 10". www.thethirdrail.net. Retrieved May 8, 2016.
- ^ a b c "South Side Rail Road". www.trainsarefun.com. Retrieved May 29, 2016.
- ^ a b "SOUTH SIDE RAILROAD". www.arrts-arrchives.com. Retrieved May 17, 2016.
- ^ Ziel & Foster (1987), pp. 30–33.
- ^ "NY&RockawayRR". arrts-arrchives.com. Retrieved May 15, 2016.
- ^ "NY&RockawayRR2". arrts-arrchives.com. Retrieved May 16, 2016.
- ^ "Cedarhurst Cutoff". www.lirrhistory.com. Archived from the original on August 29, 2000. Retrieved May 15, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ a b "PRR Chronology, 1874" (PDF)., March 2005 Edition
- ^ a b "PRR Chronology, 1876" (PDF)., April 2005 Edition
- ^ "PRR Chronology, 1877" (PDF)., April 2005 Edition
- ^ Ziel & Foster (1987), pp. 14, 52.
- ^ "At Last Steam Travel on Atlantic Avenue". Brooklyn Daily Eagle. Brooklyn, NY. March 28, 1877. p. 4.
- ^ a b c d e f "Corporate Genealogy: Long Island Railroad". Valuation Reports. 36. Interstate Commerce Commission: 47–50, 68–69. January 1932. Archived from the original on January 12, 2002.
- ^ "Municipal Excursion on the Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. July 1, 1877. p. 4.
- ^ "Rapid Transit". Brooklyn Daily Eagle. Brooklyn, NY. August 13, 1877. p. 4.
- ^ "Rapid Transit Extension". Brooklyn Daily Eagle. Brooklyn, NY. June 24, 1890. p. 1.
- ^ "Quick Time". Brooklyn Daily Eagle. Brooklyn, NY. August 22, 1877. p. 2.
- ^ "United". Brooklyn Daily Eagle. Brooklyn, NY. August 7, 1878. p. 4.
- ^ "Coney Island". Brooklyn Daily Eagle. Brooklyn, NY. October 25, 1883. p. 3.
- ^ "Coney Island". Brooklyn Daily Eagle. Brooklyn, NY. January 16, 1884. p. 3.
- ^ a b c d e f g "Manhattan Beach". www.lirrhistory.com. Archived from the original on March 4, 2000. Retrieved May 12, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ "PRR Chronology, 1878" (PDF)., June 2006 Edition
- ^ Ziel & Foster (1987), pp. 14, 36, 38.
- ^ Ziel & Foster (1987), p. 53.
- ^ a b Felix Reifschneider, History of the Long Island Railroad, 1925, reprinted winter 2001 in The Third Rail
- ^ "Corporate Genealogy: New York, Brooklyn and Manhattan Beach". Valuation Reports. 36. Interstate Commerce Commission: 71, 78. January 1932. Archived from the original on June 26, 2002.
- ^ Ziel & Foster (1987), p. 52.
- ^ Ziel & Foster (1987), p. 14.
- ^ "Corporate Genealogy: North Shore Branch". Valuation Reports. 36. Interstate Commerce Commission: 91–92, 95, 124–125. January 1932. Archived from the original on July 13, 2002.
- ^ "Not Bought by Mr. Corbin". Brooklyn Daily Eagle. Brooklyn, NY. December 10, 1886. p. 6.
- ^ "Buying Out the East River Ferry Company". Brooklyn Daily Eagle. Brooklyn, NY. July 23, 1887. p. 2.
- ^ "The Annex Running". Brooklyn Daily Eagle. Brooklyn, NY. June 2, 1887. p. 4.
- ^ "Down on Long Island". Brooklyn Daily Eagle. Brooklyn, NY. December 2, 1888. p. 9.
- ^ "Local Stocks and Bonds". Brooklyn Daily Eagle. Brooklyn, NY. March 6, 1892. p. 3.
- ^ a b Keller (2013).
- ^ Ziel & Foster (1987), pp. 82–83.
- ^ a b c d "LIRR 125 Anniversary". www.trainsarefun.com. Retrieved May 6, 2016.
- ^ "Corbin Buys the P.P. and C.I.R.R.". Brooklyn Daily Eagle. Brooklyn, NY. January 24, 1893. p. 1.
- ^ "Culver Line". www.lirrhistory.com. Archived from the original on March 3, 2000. Retrieved May 12, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ "The New Route to the Sea". Brooklyn Daily Eagle. Brooklyn, NY. August 6, 1895. p. 2.
- ^ "L Trains to the Island To-morrow". Brooklyn Daily Eagle. Brooklyn, NY. April 18, 1896. p. 1.
- ^ "Rapid Transit Plans Still Branching Out". Brooklyn Daily Eagle. Brooklyn, NY. April 3, 1899. p. 1. (continued on page 2)
- ^ "Transit Co. Leases P.P. and C.I. Road". Brooklyn Daily Eagle. Brooklyn, NY. June 17, 1899. p. 1.
- ^ "L Trains to Rockaway". Brooklyn Daily Eagle. Brooklyn, NY. July 16, 1898. p. 14.
- ^ "New Route to Jamaica". Brooklyn Daily Eagle. Brooklyn, NY. October 2, 1898. p. 4.
- ^ "Jamaica Time Table". Brooklyn Daily Eagle. Brooklyn, NY. May 21, 1899. p. 11.
- ^ "No L.I. Trains to the Bridge". Brooklyn Daily Eagle. Brooklyn, NY. May 24, 1899. p. 2.
- ^ "Cars are Running Now". Brooklyn Daily Eagle. Brooklyn, NY. May 25, 1899. p. 1.
- ^ "Service to the Beaches". Brooklyn Daily Eagle. Brooklyn, NY. July 28, 1899. p. 5.
- ^ "Long Island Railroad". Brooklyn Daily Eagle. Brooklyn, NY. September 19, 1899. p. 13.
- ^ a b c d "PRR Chronology, Discontinuance/Last Runs of Passenger Service" (PDF). Archived from the original (PDF) on March 16, 2006. Retrieved February 8, 2007., Edition of June 30, 2003
- ^ Seyfried, Vincent F. (1975). "Part Six The Golden Age 1881-1900". The Long Island Rail Road: A Comprehensive History. Long Island: Vincent F. Seyfried. Archived from the original on April 19, 2015.
- ^ Ziel & Foster (1987), p. 96.
- ^ Ziel & Foster (1987), pp. 71, 120, and 184-187.
- ^ Ziel & Foster (1987), p. 121.
- ^ "Railroad Reports". Brooklyn Daily Eagle. Brooklyn, NY. February 6, 1899. p. 8.
- ^ a b "PRR Chronology, 1905" (PDF)., March 2005 Edition
- ^ "Belmont and Peters Buy Queens Trolleys". The New York Times. June 21, 1905. p. 14.
- ^ "Company Profile". Jamaica Buses. Archived from the original on January 25, 2006.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ PRR Chronology, 1926 (2004).
- ^ "Belmont Park Open". The New York Times. May 5, 1905. p. 1. Retrieved October 15, 2009.
- ^ "Belmont Park's Crowds". The New York Times. May 7, 1905. p. 22. Retrieved October 15, 2009.
- ^ "Electric to Belmont Park". The New York Times. September 26, 1905. p. 7. Retrieved October 15, 2009.
- ^ Huenke, Athur J. "Belmont Park Race Track". Arrt's Arrchives. Retrieved October 15, 2009.
- ^ Sisto, Ernest (May 26, 1957). "Belmont, at Halfway Point in $6,00,000 Rebuilding, Opens Meet Wednesday". The New York Times. Retrieved October 15, 2009.
- ^ "Atlantic Avenue Improvement". www.lirrhistory.com. Archived from the original on June 21, 2000. Retrieved May 13, 2016.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ "PRR Chronology, 1925" (PDF)., June 2004 Edition
- ^ "PRR Chronology, 1927" (PDF)., July 2004 Edition
- ^ "PRR Chronology, 1928" (PDF)., July 2004 Edition
- ^ Charles L. Sachs, The Blessed Isle: Hal B. Fullerton and His Image of Long Island, 1897–1927, Interlaken, NY: Heart of the Lakes Publishing, 1991.
- ^ "WHBrEL". www.arrts-arrchives.com. Retrieved April 28, 2016.
- ^ "LIRR Branch Notes". www.trainsarefun.com. Retrieved April 28, 2016.
- ^ "Underutilized Tracks: A Chronicle of Electric Train Service to East Williston and a History of the Neighboring Communities". Derek Stadler. November 15, 2014. Retrieved May 27, 2016.
- ^ "Dec 04.pdf PRR Chronology, 1950"., December 2004 Edition
- ^ a b Ziel & Foster (1987), p. 277.
- ^ a b Jacobs (1988), p. 108.
- ^ "PRR Chronology, 1949" (PDF)., September 2004 Edition
- ^ "oct31955". www.arrts-arrchives.com. Retrieved May 8, 2016.
- ^ Ziel & Foster (1987), pp. 271–272.
- OCLC 834874.
- ^ "Long Island Expressway (I-495)". www.nycroads.com. Retrieved May 22, 2016.
- ^ a b "Tip of the North Fork: History of Rail Service to Greenport and Surrounding Territory". Derek Stadler. February 21, 2016. Retrieved June 1, 2016.
- ^ Ziel & Foster (1987), pp. 27, 281, and 312.
- ^ LIRR Rononkoma Branch Timetable[permanent dead link]
- ^ Ziel & Foster (1987), p. 289.
- ^ a b c d e "North Fork Rail Stations: A Brief History of Southold Town and its Railroad Way Stations". Derek Stadler. September 1, 2015. Retrieved May 29, 2016.
- ^ "LIRR Road n' Rail". www.trainsarefun.com. Retrieved May 29, 2016.
- ^ "Discontinued Station Stops: The History of the Moriches and the Termination of Railroad Service". Derek Stadler. February 2, 2014. Retrieved May 29, 2016.
- ^ a b Better Rail Service for Nassau County (PDF). Nassau County Planning Commission. June 1963. Archived from the original on May 17, 2014.
{{cite book}}
: CS1 maint: unfit URL (link) - ^ Ziel & Foster (1987), p. 293.
- ^ a b c d e f Sturm (2014).
- ^ Jacobs (1988), p. 121.
- ^ Lynch, Steve. "LIRR MP15-AC Engine Roster". Trainsarefun.com LIRR History Archive. Retrieved February 27, 2012.
- ^ "PRR Chronology, 1970" (PDF)., June 2005 Edition
- ^ a b "LIRR Grade Crossing Eliminations". www.trainsarefun.com. Retrieved May 22, 2016.
- New York Times, Electric Service Extended by L.I.R.R., December 31, 1987, section B, page 3
- ^ "L.I.R.R. FARE RISE SEEN AS SUBWAY SUBSIDY". The New York Times. July 12, 1981. Retrieved November 24, 2019.
- ^ RARE Long Island Rail Road LIRR Bronze Medal / Coin 150 Years of Service (WorthPoint)
- ^ Doherty, Matthew (November 7, 2004). "Far West Side Story". The New York Times. Retrieved March 6, 2010.
- ^ a b c Voboril, Mary (March 26, 2005). "The Air Above Rail Yards Still Free". Newsday. New York.
- ^ Blumenthal, Ralph (February 21, 1984). "Problems Halt Laying of Pipe at L.I.R.R. Project". The New York Times. Retrieved March 5, 2010.
- ^ "West Side Rail Yard (Request for Proposals for Development)". Metropolitan Transportation Authority. July 13, 2007. Archived from the original on March 23, 2010. Retrieved March 6, 2010.
- ^ "2004 Annual Report" (PDF). Metropolitan Transportation Authority. p. 66. Archived from the original (PDF) on March 13, 2009. Retrieved March 6, 2010.
- ^ LIRR Official Hillside Facility brochure (Unofficial LIRR History Website)[usurped]
- ^ Draffen, Duayne (April 28, 1998). "16 Years After Death of 9 Teen-Agers, Rail Bridge Opens". The New York Times. Retrieved May 29, 2016.
- ^ Clines, Francis X. (December 9, 1993). "Death on the L.I.R.R.: The Rampage; Gunman in a Train Aisle Passes Out Death". The New York Times. Retrieved November 4, 2009.
- ISSN 0362-4331. Retrieved December 22, 2022.
- ^ "New York & Atlantic Railway". Anacostia and Pacific Company. Archived from the original on February 2, 2007.
- ^ "New York & Atlantic Railway". www.trainsarefun.com. Retrieved May 8, 2016.
- ^ William J. Skeets (June 2005). "New York & Atlantic Railway". The Railroad Press – via www.trainsarefun.com. p. 32 p. 33 p. 34 p. 35 p. 36
- ISSN 0362-4331. Retrieved December 22, 2022.
- ^ Sengupta, Somini (March 15, 1998). "End of the Line for L.I.R.R.'s 10 Loneliest Stops". The New York Times. Retrieved May 13, 2016.
- ^ gregorygrice (April 10, 2013), RARE! LIRR SW1001 Hauls Overheated Montauk Train From LIC & Back (DE30AC #411), archived from the original on December 14, 2021, retrieved May 13, 2016
- ^ Metropolitan Transportation Authority Announces Historic Restructuring, press release dated October 9, 2002
- ^ a b c "Railroad Accident Brief RAB-09-01" (PDF). www.ntsb.gov. March 13, 2009 [2006]. p. 1. Retrieved March 30, 2020.
- "Passenger Fatality on Long Island Rail Road". National Transportation Safety Board. Archived from the original on January 3, 2015.
- ^ "Mother Of Teen Who Died In LIRR Train Gap Commits Suicide". NBC New York. May 19, 2009. Archived from the original on March 30, 2020. Retrieved March 30, 2020 – via Associated Press.
- ^ Castillo, Alfonso A. (June 24, 2009). "NTSB: Series of circumstances led to gap fall death". Newsday. Retrieved March 30, 2020.
- ^ "PTSB ISSUES INTERIM RECOMMENDATIONS IN GAP INVESTIGATION : Long Island Railroad Already Implementing Measures" (Press release). New York State Department of Transportation. November 1, 2006. Archived from the original on March 22, 2019. Retrieved March 30, 2020.
- ^ "MTA Picks Helena Williams to Head Long Island Rail Road" (Press release). New York Metropolitan Transportation Authority. June 4, 2007. Retrieved August 9, 2007.
- ISSN 0041-0934.
- ^ Castillo, Alfonso A. (April 23, 2009). "Special trip marks LIRR's 175th anniversary". Newsday. Retrieved October 14, 2009.
- ^ Neuman, William (May 11, 2007). "Awaiting Rock-Eating Beast, L.I.R.R. Tunnel Is Poised to Finish Trip to Grand Central". The New York Times. Retrieved February 3, 2018.
- )
- ^ Siff, Andrew (April 16, 2018). "MTA Megaproject to Cost Almost $1B More Than Prior Estimate". NBC New York. Retrieved April 16, 2018.
- ^ Castillo, Alfonso A. (April 15, 2018). "East Side Access price tag now stands at $11.2B". Newsday. Retrieved April 16, 2018.
- ^ Castillo, Alfonso A. (December 19, 2022). "LIRR shuttle service to start before full opening of Grand Central Madison". Newsday. Retrieved December 19, 2022.
- ^ Hoogensen, Finn (December 19, 2022). "LIRR to offer direct train between Grand Central Madison and Jamaica, Queens". PIX11. Retrieved December 22, 2022.
- ^ Anuta, Joe; Newman, Philip (June 5, 2013). "Queens Tomorrow: LIRR headed to Grand Central". TimesLedger. TimesLedger Newspapers. Archived from the original on May 25, 2018. Retrieved May 24, 2018.
- ^ a b c d "MTA Long Island Rail Road Committee Meeting" (PDF). mta.info. Metropolitan Transportation Authority. November 2017. p. 35. Retrieved May 24, 2018.
- ^ Kulick, Beth (2014). "Jamaica Interlocking Reconfiguration Operations Simulation" (PDF). apta.com. TranSystems Corporation. Archived from the original (PDF) on March 5, 2016. Retrieved February 5, 2018.
- ^ Wendy Karpel Kreitzman (November 19, 2010). "MTA Announces Second Pocket Track Proposed for LIRR in Great Neck". Great Neck Record. Archived from the original on December 9, 2010. Retrieved May 24, 2018.
- ^ "Mid-Suffolk Yard". mta.info. Archived from the original on July 18, 2018. Retrieved December 8, 2018.
- ^ "Long Island Rail Road Double Track Project" (PDF). mta.info. Metropolitan Transportation Authority. February 2013. Archived from the original (PDF) on August 26, 2014. Retrieved April 10, 2015.
- ^ "news - LIRR Opens Ronkonkoma Branch Double Track". MTA. September 21, 2018. Retrieved September 22, 2018.
- ^ "LIRR Double Track project completed ahead of schedule". ABC7 New York. September 21, 2018. Retrieved September 22, 2018.
- ^ Castillo, Alfonso A. (October 29, 2012). "LIRR halted, still affected by storm". Newsday. Retrieved December 8, 2018.
- ^ "Full service restored on Long Island Railroad". The Island Now. December 13, 2012. Retrieved December 8, 2018.
- ^ "LIRR still years away from some Sandy repairs". Newsday. October 30, 2018. Retrieved December 8, 2018.
- ^ "Officials: More than 100 hurt in LIRR train derailment". Newsday. January 4, 2017. Retrieved January 4, 2017.
- ^ McLaughlin, Aidan. "LIRR train derails, injuring 103 people in Brooklyn at Atlantic Terminal". New York Daily News. Retrieved January 4, 2017.
- ^ "LIRR Train Strikes Car". March 24, 2018.
- ^ "Witness: Car in train collision was involved in previous crash". News 12 Long Island. February 26, 2019. Archived from the original on February 27, 2019.
- ^ "MTA - Planning Studies". Metropolitan Transportation Authority. Archived from the original on March 6, 2014.
- ^ "Main Line Corridor Improvements Project Presentation" (PDF). Metropolitan Transportation Authority. Retrieved January 7, 2016.
- ^ Fitzsimmons, Emma G. (January 5, 2016). "Cuomo Revives Long-Stalled Plan to Add Track to L.I.R.R." The New York Times. p. A18. Retrieved January 7, 2016.
- ^ "LIRR Third Track Project Moving Forward Despite Concerns Of Residents". CBS New York. September 5, 2018. Retrieved September 6, 2018.
- ^ Rivoli, Dan (September 5, 2018). "Cuomo continues infrastructure tour with Long Island Rail Road groundbreaking". New York Daily News. Retrieved September 6, 2018.
- ^ Berger, Paul (December 13, 2017). "MTA Awards $1.8 Billion Contract to Expand Long Island Rail Road". The Wall Street Journal. Retrieved January 25, 2018.
- ^ "LIRR unveils 1st section of new express lane track". Yahoo! Sports. August 15, 2022. Retrieved August 15, 2022.
- ^ Duggan, Kevin (October 3, 2022). "'Third' time's the charm: MTA finishes $2.5 billion LIRR Third Track project". amNewYork. Retrieved October 15, 2022.
- ^ "LIRR Completes Third Track Project". Railway Age. October 4, 2022. Retrieved October 15, 2022.
References
Pennsylvania Railroad Technical & Historical Society
- PRR Chronology, 1835 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1835" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1837 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1837" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1862 (May 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1862" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1864 (May 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1864" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1865 (May 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1865" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1866 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1866" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1867 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1867" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1868 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1868" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1869 (June 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1869" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1870 (October 2015). Baer, Christopher T. (ed.). "PRR Chronology, 1870" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - PRR Chronology, 1926 (June 2004). Baer, Christopher T. (ed.). "PRR Chronology, 1926" (PDF). Retrieved December 4, 2017.
{{cite web}}
: CS1 maint: numeric names: authors list (link)
Other sources
- Fischler, Stan (2007). Long Island Rail Road. MBI Railroad Color History. St.Paul, MN: Voyageur Press. OCLC 71581509.
- Hinsdale, Elizur Brace "E.B." (1831–1916) (1898). History of the Long Island Railroad Company, 1834–1898. )
- Jacobs, Timothy (1988). History of the Pennsylvania Railroad. Bison Books Corporation. OCLC 948503076.
- Keller, David (October 28, 2013). Foreword. Long Island Rail Road: Port Jefferson Branch. By Morrison, David D. Arcadia Publishing. ISBN 9781467120135.
- Smith, Mildred H. (1958). Early History of the Long Island Railroad, 1834-1900. Uniondale, Long Island, NY: Salisbury Printers. LCCN 58-59530.
- Sturm, Robert C. (September 1, 2014). The Long-Island Rail-Road Company a History 1834 - 1965. Long Island Sunrise Trail Chapter - National Railway Historical Society. ISBN 978-0-9886-9164-3.
- Ziel, Ron; Foster, George H. (1987). Steel Rails to the Sunrise (Revised ed.). Mattituck, NY: Amereon House. OCLC 18506373.